Final certificate for construction contracts
Contents |
[edit] Introduction
The final certificate is certification by the contract administrator that a construction contract has been fully completed. It is issued at the end of the defects liability period and has the effect of releasing all remaining money due to the contractor, including any remaining retention.
The value of the final certificate will be based on the final account agreed by the cost consultant and the contractor. This means that all patent defects must have been remedied, all adjustments to the contract sum must have been agreed and all claims settled.
Where proceedings have been commenced in relation to a dispute, the conclusiveness of the final certificate is subject to the findings of those proceedings. In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication, arbitration or other proceedings may then be necessary to resolve the dispute. The final certificate is then only conclusive in relation to matters that are not disputed.
If the client intends to pay a different amount from that shown on the certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice - see Housing Grants, Construction and Regeneration Act for more information).
[edit] Alternative procedures
In design and build contracts (such as Joint Contracts Tribunal (JCT) DB 16) the final certificate may be described as the final statement.
In construction management contracts, where there are a number of trade contracts, final statements are issued for each trade contract. Once final statements have been issued for each trade contract, the construction manager co-ordinates preparation of the final report and issues the final certificate for the whole project.
There is a similar procedure on management contracts, where final certificates are issued by the management contractor for each individual works contract, and then once all works contracts have received a final certificate, the management contractor provides the client's contract administrator (or cost consultant) with information allowing them to calculate the prime cost (the cost of the works contracts) and a final certificate is issued to the management contractor.
[edit] Alternative meaning
Rather confusingly, the term 'final certificate' can also refer to a completion certificate issued by a building control body in relation to the building regulations.
Manual to the Building Regulations: A code of practice for use in England, published by HM Government in July 2020, states: ‘Final certificate refers to the certificate issued by the approved inspector to the person carrying out the work and the local authority and confirms that the work in the initial notice is complete and that the approved inspector is satisfied that it complies with the relevant requirements of the Building Regulations.’
See Building regulations completion certificate for more information.
[edit] Related articles on Designing Buildings Wiki
- Building regulations completion certificate.
- Certificates in the construction industry.
- Contract administrator.
- Defects liability period.
- Final account.
- Housing Grants, Construction and Regeneration Act.
- Retention.
- Interim certificates.
- Sectional completion.
- Topping out.
- What is a final account.
- Work-to-complete list.
Featured articles and news
Insights of how to attract more young people to construction
Results from CIOB survey of 16-24 year olds and parents.
Focussing on the practical implementation of electrification.
Sustainable Urban Drainage and Biodiversity
Awards for champions of these interconnected fields now open.
Microcosm of biodiversity in balconies and containers
Minor design adaptations for considerable biodiversity benefit.
CIOB student competitive construction challenge Ireland
Inspiring a new wave of Irish construction professionals.
Challenges of the net zero transition in Scotland
Skills shortage and ageing workforce hampering Scottish transition to net zero.
Private rental sector, living standards and fuel poverty
Report from the NRH in partnership with Impact on Urban Health.
.Cold chain condensing units market update
Tracking the evolution of commercial refrigeration unit markets.
Attending a conservation training course, personal account
The benefits of further learning for professsionals.
Restoring Alexander Pope's grotto
The only surviving part of his villa in Twickenham.
International Women's Day 8 March, 2025
Accelerating Action for For ALL Women and Girls: Rights. Equality. Empowerment.
Lack of construction careers advice threatens housing targets
CIOB warning on Government plans to accelerate housebuilding and development.
Shelter from the storm in Ukraine
Ukraine’s architects paving the path to recovery.
BSRIA market intelligence division key appointment
Lisa Wiltshire to lead rapidly growing Market Intelligence division.
A blueprint for construction’s sustainability efforts
Practical steps to achieve the United Nations Sustainable Development Goals.
Timber in Construction Roadmap
Ambitious plans from the Government to increase the use of timber in construction.
ECA digital series unveils road to net-zero.
Retrofit and Decarbonisation framework N9 launched
Aligned with LHCPG social value strategy and the Gold Standard.
Comments
What does a 'Part Final Certificate' mean? Does it mean for the specified works it is fully complete (but there are other works as part of the application) Or that the specified works are part complete?
This might relate to a final certificate for part of the works - ie where there is partial possession or sectional completion - see the comments at the end of those articles.
However, the specific term 'part final certificate' is more commonly used in relation to building regulations approvals.