Abatement in construction
Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect. Abatement only applies to payment for labour and materials, not to professional services or to losses resulting from delay or disruption. Abatement exists as a common law right.
Abatement is often confused with set off. Set off (or contra charging) requires that a breach of contract can be demonstrated. It can permit the withholding or extinguishing of an agreed payment. Set off can be used to recover the costs of rectifying defects and any delay. Whilst set off is often accompanied by a counterclaim it is to be distinguished in that set off cannot, unlike a counterclaim, give rise to a positive balance of claim. Set off rights can either be contractual, equitable or in the case of insolvency, statutory.
Before the 2011 amendments to the Housing Grants Construction and Regeneration Act, set off and counterclaim were only permitted if a withholding notice was issued, whilst abatement did not require a withholding notice as the value of the works had been reduced and there was only an obligation to pay the amount properly due.
Since 2011 however, set off, counterclaim and abatement all require that a pay less notice is issued.
[edit] Related articles on Designing Buildings
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.
Comments
Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect.