Articles of agreement
Contents |
[edit] Introduction
Contract documents for a construction contract will typically consist of:
- Contract drawings.
- Priced bill of quantities.
- Articles of agreement.
- Contract conditions.
- For contracts where there is a contractor’s designed portion: employer’s requirements, contractor’s proposals and contract sum analysis.
The ‘articles of agreement’ set out the core obligations of the parties involved. Typically, they consist of four sections:
- Recitals.
- Articles.
- Contract Particulars.
- Attestation.
By way of an example, the contents of the articles of agreement in the JCT Standard Building Contract (SBC) are set out below in more detail.
[edit] Recitals
Recitals contextualise the agreement, giving factual explanations for the basis of the contract. Seven recitals describe what is required and the events that have taken place.
[edit] First recital
Describes the work required by the employer, identifies the site, confirms the preparation of the design and bill of quantities.
[edit] Second recital
Confirms that a priced copy of the bill of quantities has been supplied by the contractor to the employer, with a priced activity schedule where required.
[edit] Third recital
Identifies the contract drawings.
[edit] Fourth recital
Identifies whether the employer is to be considered a contractor for tax deduction purposes under the Construction Industry Scheme.
[edit] Fifth recital
Refers to an information release schedule provided to the contractor by the employer (this is optional).
[edit] Sixth recital
Clarifies whether the works are to be carried out in sections.
[edit] Seventh recital
This only applies (along with three more recitals), where the contractor is obliged to complete design works under the provisions for a contractor’s designed portion.
[edit] Articles
These set out what is agreed between the parties.
[edit] Article 1
The obligation of the contractor, i.e. undertaking and completing the works subject to the contract documents.
[edit] Article 2
The obligation of the employer, i.e. to pay the contract sum or such other sum as becomes payable under the contract (through variations and/or correction of errors).
[edit] Article 3
Identifies the architect (or contract administrator) under the contract, and provides the employer with the power to maintain someone in the role of duty-holder (or employer’s agent).
[edit] Article 4
Identifies the quantity surveyor.
[edit] Article 5
Identifies the principal designer.
[edit] Article 6
Identifies the principal contractor.
[edit] Article 7
Makes reference to the right to adjudication in the event of any dispute.
[edit] Article 8
Makes reference to the right to arbitration in the event of any dispute.
[edit] Contract particulars
This section sets out the aspects of the contract that are particular to the project to which the contract relates. It is a schedule for the variables in the agreement and conditions. It is important that the variables are compatible with the relevant operating mechanism in the agreement, conditions and schedules as disputes may arise when either party applies the contract particulars information without proper reference to the operating clause.
Read more about contract particulars here.
[edit] Attestation
The attestation is the process of confirming that something is correct or genuine, or that a particular requirement has been met. It may be completed:
[edit] Under seal
Signed by both parties, witnessed and made clear that it is executed as a deed.
[edit] Under hand
A ‘simple contract’ that is signed just by the parties.
[edit] Related articles on Designing Buildings Wiki
- Agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Contract execution.
- Contract negotiation.
- Contracts under seal v under hand.
- Essentials of a contract.
- FIDIC.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Named specialist work.
- NEC3.
- Period for reply.
- Procurement route.
- Sub-contract.
- Z clauses.
[edit] External references
- ‘The JCT 05 Standard Building Contract’ (2nd ed.), NDEKUGRI, I., RYCROFT, M., Butterworth-Heinemann (2009)
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.