Period for reply
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. The third edition, NEC3 was published in 2005.
Many clauses within the NEC suite of contracts establish a period within which a task must be completed by referring to defined dates such as the ‘completion date’, the ‘defects date’, and so on. Some clauses establish a period within which one of the parties must respond to a communication from the other, such as the period for the submission of quotations for compensation events, acceptance of the programme and so on. However, where no such period has been prescribed, then the ‘period for reply’ applies.
The Engineering Construction Contract (ECC) states that:
‘If this contract requires the project manager, the supervisor, or the contractor to reply to a communication, unless otherwise stated in this contract, he or she replies within the period for reply.’
The period for reply is set out in the contract data part one, completed by the employer, and replies to communications must be made within that period, unless another period is stated in the contract. Where a specific time limit is defined within the contract for a particular reply then this will take precedence over the period for reply.
If the project manager fails to reply to a communication within the period for reply, this may constitute a compensation event. If the contractor fails to reply to a communication, then an adjustment may be made to the next payment reflecting the cost to the employer.
An exception to this is where the project manager and contractor agree to an extension before the reply is due.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Articles of agreement.
- Compensation event.
- Contract conditions.
- Defects.
- Delay damages.
- Disallowed cost.
- Extension of time.
- Key dates.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Procurement route.
- Time Risk Allowance TRA.
- Variations.
- Z clauses.
[edit] External references
- ‘The New Engineering Contract: A Legal Commentary’, McINNIS, A., Thomas Telford (2001)
Featured articles and news
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
Comments