Design and build: outline work plan
This is an outline work plan for a private sector design and build project. For other procurement routes, including public sector projects (which may be design and build), click here.
Clicking on the stages will open a detailed schedule of the tasks necessary to complete that stage. Together these tasks represent a single, consolidated project plan from the first moment it becomes apparent a project might be required, right through to post occupancy evaluation.
Design and build
Stage 1: Business justification.
Stage 2: Feasibility studies.
Stage 3: Project brief.
Stage 4a: Concept design (design by consultant team).
or
Stage 4b: Concept design (design by contractor).
Stage 5a: Detailed design (design by consultant team).
or
Stage 5b: Detailed design (design by contractor).
Stage 6: Production information.
Stage 7: Mobilisation.
Stage 8: Construction.
Stage 9: Occupation and defects liability period.
Stage 10: Post occupancy evaluation.
Moveable stages:
- Appointing consultants.
- Planning permission (design by consultants).
- Tender.
- Planning permission (design by contractor).
Notes
- Design and build projects involve appointing a contractor to design the development and also to construct it. The contractor might be appointed early in the project to carry out all of the design work, or later in the project to complete a design which others have begun. This means that design tasks can be attributed either to a consultant team or the contractor depending on whether the contractor has been appointed or not. As a consequence, we include two versions of the concept design stage, detailed design stage and also the process for applying for planning permission. The tender stage is moveable depending on when the contractor is appointed.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.


















Comments