Working up construction works
Contents |
[edit] Introduction
Working up (or creating a workup) refers to the process of collating the details of the measured elements of construction works before prices have been determined. This information is then used to produce an unpriced bill of quantities (BoQ).
An unpriced bill of quantities (BoQ) is essentially an estimate in the form of a template. It breaks down the work required on a project into tasks but has no measured quantity (or price) by each task. For more information see: Unpriced bill of quantities.
[edit] Taking off
Before working up takes place, elements are identified through the taking off process. The term taking off refers to the process of identifying elements of construction works that can be measured and priced. This is necessary to produce bills of quantities and requires that the design is complete and a specification has been prepared.
Analysis of drawings and specifications allows the cost consultant (usually a quantity surveyor) to prepare a taking off list, which lists all of the individual elements that comprise the works.
For more information see: Taking off.
[edit] Workup sheets
The process of taking off includes calculating measurements of the components by number, length, area, volume, weight or time. All items must be accounted for through the take off process. This information is then entered on workup sheets.
Quantities from workup sheets are generally grouped based on work category. This information is then transferred to a summary sheet for pricing.
[edit] Workup and property purchasing
In the United States, the term workup can also be used to describe an estimate created for a prospective purchaser of a building lot, including the plan and options. In this instance, the workup takes place before the purchase agreement is signed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
AI and automation in 3D modelling and spatial design
Can almost half of design development tasks be automated?
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
The maintenance challenge of tenements.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.