Tree dripline
The dripline is the guide measurement used to prevent unnecessary damage to trees during construction works. It is defined as the outermost circumference of the tree’s canopy, from which water drips onto the ground. The ‘dripline area’ is taken to include the soil and roots that lie within that circumference.
It is crucial for the stability and health of a tree that the dripline area is ‘off limits’ from any construction activity. It may be necessary to erect a fence around the dripline or, if possible, further out around groups of trees so as to prevent their roots from being damaged by construction plant, or by works such as excavation, soil compaction or consolidation. Fences should remain in place until all construction work is complete, including the final grading and smoothing of the site.
If work inside the dripline is unavoidable, only hand tools should be used. Where possible, tunnels should be excavated beneath the root system as opposed to trenching. Other measures that can be adopted to avoid undue damage include:
- Using porous paving materials such as brick or flagstone rather than concrete or asphalt.
- Not raising the grade of the soil inside the dripline by more than a few inches.
- Not lowering the grade of the soil inside the dripline by more than 2 inches.
- Not piling soil or construction materials inside the dripline, even for a short period of time.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Registered building inspectors
Building types and conflicts of interest updates explaineed.
Engineering services still struggle with labour shortages
According to latest quarterly services survey of the sector.
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.