Extension of time request
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. In the United States, this is described as a time extension. The UK equivalent is an extension of time (EOT). Fore more information see: Extension of time.
Time extensions may be granted if the contractor can demonstrate that the delay was caused by events beyond their control. The contract will typically specify the circumstances and format in which a time extension request may be made.
A request will commonly include the following details:
- The delay that has been incurred and the affected activities.
- The specific issues that caused the delay.
- What steps have been taken to mitigate the delay.
- Schedule or cost adjustments that have been made to try and reduce the impact of the delay.
- The contract clause that allows the request.
- The amount of time being requested (in calendar days) and the proposed recovery plan.
- Supporting documents, such as; photographs, video footage, timesheets, and so on.
- Evidence of communications warning of possible delays.
In submitting the time extension request, the contractor must consider that calendar days are not the same as working days, that insurances and other bonds may need to be re-issued to cover any agreed extension period, and no further time will need to be requested relating to the same events.
If they approve the request, the project manager must reply by letter and issue a change order. The contract may specify a time frame within which time extension requests should be submitted and a response issued.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.