Tender settlement meeting for construction
The tender settlement meeting is part of the pre-contract planning process, held just before the contractor submits their tender to the client. The estimate is converted to a tender for senior management to review and assess whether it complies with the client’s requirements as stated in the tender instructions.
Commercial and technical matters are checked to ensure that scheduling, pricing and sequencing are accurate, as well as sub-contractor arrangements and that the risk that will be incurred should they be awarded the contract has been properly considered. Decisions will often be made on the basis of how much the contractor needs the work, their level of confidence in their ability to provide the work as stated in the tender, and their level of comfort with any assumptions that may have been made in the estimate.
The meeting should have formal minutes taken which set down the decisions reached. As well as reviewing all aspects of the bid, there may be other decisions to be made before proceeding with submission to the client. The most common of these include:
- If nothing is specified in the invitation to tender, what documents, if any, should be submitted with the tender? Some contractors prepare additional information such as a company profile brochure or tender stage construction programme that they hope will make their bid stand out from the others.
- Has an alternative design or method been offered? If so, another price may need to be settled by the review panel.
- Qualifications, which vary the requirements of the tender documents, are generally not permitted by clients. However, some circumstance may require them, so management must decide on a suitable approach and review whether any qualifications are likely to result in the tender being rejected.
- Do the tender documents require a fully priced bill of quantities or is this only required if the tender is being seriously considered for acceptance?
- Evaluation of the risks that may have been taken during the estimating process (were certain factors assumed or decisions taken on a basis of probability?).
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Form of tender.
- Invitation to tender.
- Margin.
- Mid-tender interviews.
- Pre-tender interviews.
- Procurement route.
- Selective tendering.
- Serial tendering.
- Tender documentation.
- Tender evaluation.
- Tender for supply contracts.
- Tender processes for construction contracts.
- Tender settlement.
[edit] External references
- ‘Introduction to Estimating for Construction’, GREENHALGH, B., Routledge (2013)
Featured articles and news
Biodiversity and the built environment digital series
The nature of building, with CIOB and CWP.
A call for prevention and sensitive re-use.
Risks to the long-term effectiveness of the BNG scheme
National Audit Office publish review of Biodiversity Net Gain.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Building Safety recommendations and Northern Ireland
The NI roadmap to improving safety in high rise residential.
BSA residential sector competence standards guidance
BSAS 01:2024 Organisational Capability Management System Standard - Competence Assurance.
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.