Reserved matters in planning permissions
Outline planning applications can be used to find out whether a proposed development is likely to be approved by the planning authority, before substantial costs are incurred developing a detailed design. Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage.
Reserved matters, also refers certain matters concerning the governance of the UK, where decisions may be taken by the UK Parliament at Westminster even though they have an effect in Scotland, Wales, Northern Ireland or the regions of England. Such reserved matters may also give allowance for devolved governments to implement slightly different regimes, though more directly, where matters are accepted areas where decision-making has been delegated by Parliament to the devolved institutions such as the Scottish Parliament, the Assemblies of Wales, Northern Ireland and London or to Local Authorities, these are referred to as devolved matters.
In terms of reserved matters and outline planning applications on the 10 August 2006, changes to the outline planning permission process came into force intended to make outline planning applications more 'detailed' and so to restrict the extent of reserved matters. Reserved matters that might be the subject of further applications once outline planning consent has been obtained can now include:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed in any way.
Outline permission is not a permission to start work on site. The permission notice will state which matters have been reserved for later approval. When all of the reserved matters have been approved, work may begin on the site.
Reserved matters applications should be submitted within 3 years of outline permission being granted.
Outline planning permission lasts for two years from the date reserved matters were approved, or three years from the date of the outline planning permission, whichever is the later.
[edit] Related articles on Designing Buildings
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Comments
If a reserved matters application in respect of a new road junction from a possible new housing development onto the main highway is unsupported by Highways England, on the grounds of unachievable visibility splay distances, must the Local Authority then turn down that application? What then happens to the original planning application for that access road, which was previously approved?