Specific performance in construction contracts
Specific performance is an equitable remedy available for breach of contract which requires the contract breaker to fulfil their contractual obligations.
Specific performance is not a right, but may be granted at the court’s discretion (as opposed to damages, a contractual remedy available as of right if the claimant proves its loss) in addition to, or instead of damages.
So, for example, where a binding contractual obligation has been entered into to give collateral warranties, in the event of failure to give the warranty, the other party to the principal contract could apply to the Court for an order of specific performance requiring the warranty to be entered into. For such an application to be successful, the wording of the contractual obligation will have to be clear and unambiguous.
In the case of Liberty Mercian Limited v Cuddy Civil Engineering Limited and others, Mr Justice Ramsey decided that whilst the unperformed primary obligations arising from a contract cease on termination, ancillary rights or obligations which have accrued from the performance of the contract, for example, the provision of performance bonds or warranties, survive termination. These are continuing obligations which must be honoured despite the fact that the main contract has come to an end. The Claimant was therefore entitled to the remedy of specific performance to enforce the delivery of executed warranties.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
How orchards can influence planning and development.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.