Procurement Route Pros & Cons
Contents |
[edit] Traditional Procurement
Good for:
- QUALITY – full design pre tender
- DESIGN FLEXIBILITY – variations & instructions
- SPECIALIST SUB-CON’S – Named specialist update sbc11
- DESIGN CONTROL – through arch/CA
- CDPs – eg. M&E
- COMPLEX
- COST – lump sum cost benefits unless multiple changes made
Not Suited for:
- TIME – req full detailed pack pre tender
- COST – not a benefit if many changes made
- INCOMPLETE DRAWINGS – lead to delay, costs and claims of negligence
Contract: SBC11
- LUMP SUM PAYMENT
- CDM
- CDP’s
- NAMED SUB CONTRACTORS
- VARIATIONS/INSTRUCTIONS
- RETENTION
- COLLATERAL WARRANTIES
- TERMINATION PROVISIONS
- PREAGREED ALT DISPUTE RESOLUTION
[edit] D&B Procurement
Good for:
- TIME – Fast track, overlap design & construction
- COST – lump sum/ GMP
- SINGLE POINT RESPONSIBILITY – Contractor design and build responsibility
- COMPLEX
- NOVATION – can benefit quality. Prior knowledge, sub-con drawing review
- CLIENT RISK LOW
- NAMED SUB-CON – in employers requirements
Not suited for:
- QUALITY – cheapest route to meet contract spec can lead to low quality products/ build quality.
- DESIGN FLEXIBILITY – request for change – costs/time implications
Contract: DB11
- CONTRACTOR TO COMPLETE DESIGN +CARRY OUT WORKS
- LUMP SUM/GMP
- CDM
- COLLATERAL WARRANTIES
- TERMINATION PROVISIONS
- RETENTION
- PRE AGREED DISPUTE RESOLUTION
[edit] Management Contracting Procurement
Good for:
- COMPLEX/SPECIALIST – individually appointed packages to best suited sub-contractor
- POTENTIAL COST SAVING – Competitive tender
- TIME – Overlap design/construction
- QUALITY – each package subcontracted to specialist
- DESIGN FLEXIBILITY – changes can be made throughout construction. Potential costs.
Not suited for:
- INEXPERIENCED – risk high
- FIXED COST - Prime cost basis per package. Fluctuations.
- LACK OF AVAILABLE SPECIALISTS – would leave gaps in work to be undertaken.
Contract: MC11
- PRIME COST CONTRACT
- PROVISIONS FOR COLLATERAL WARRANTIES
- SUSTAINABILITY
- COLLABERATIVE WORKING
- THIRD PARTY RIGHTS – funder-contractor
[edit] Construction Management Procurement
Good for:
- COMPLEX/SPECIALIST - individually appointed packages to best suited sub-contractor
- TIME - Overlap design/construction
- DESIGN FLEXIBILITY - changes can be made throughout construction. Potential costs.
- POTENTIAL COST SAVING - Competitive tender
- QUALITY - each package subcontracted to specialist
- ALL BUILDING TYPES
- EFFICIENCY – Early appointment of CM to aid programme
Not suited for:
- UNEXPERIENCED EMPLOYER – risk high as appointing trade contractors
- FIXED COST- Prime cost basis per package.
- LACK OF AVAILABLE SPECIALISTS
Contracts:
CM/TC11
CM/A
- EMPLYER – CM
- COLLATERAL WARRANTIES
- SUSTAINABILITY
Featured articles and news
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
AI and automation in 3D modelling and spatial design
Can almost half of design development tasks be automated?
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
The maintenance challenge of tenements.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.