Pre-qualification questionnaire PQQ for construction contracts
A pre-qualification questionnaire (PQQ, sometimes referred to as a supplier assessment questionnaire) sets out a series of questions for potential tenderers to answer regarding their level of experience, capacity and financial standing. The answers to these questions enable the client to produce a short list of suppliers that are likely to be most appropriate for their project. Short-listed suppliers may then be invited to tender for the contract.
Using a pre-qualification questionnaire has the effect of reducing the number of potential tenders to those that are genuinely appropriate for the project, saving a great deal of wasted time for potential tenderers who would not have any realistic chance of winning the contract. It also saves time for the client processing and assessing inappropriate tenders.
Pre-qualification questionnaires should be focused and simple to complete, (perhaps with limits to the number of words that can be submitted in response to each question) otherwise they may just replicate the tender process itself. They should also make it very clear what the tender process is for, so potential tenderers can properly assess whether they have the appropriate experience, capacity and financial standing.
Where possible a scoring and weighting system should be prepared for rating submitted information and potential tenderers should be informed of the details of the system that will be used.
The information requested should be straight-forward, relevant and proportionate to the size of the contract. It might request:
- Company details (including legal status).
- Details of insurance cover.
- Financial information (such as recent accounts).
- Relevant experience.
- Information about technical and professional ability.
- Information about capability and capacity.
- Health and safety policy.
- Quality assurance policy.
- Environmental management policy.
- Equal opportunities policy.
- Relevant references.
- A BIM assessment to determine BIM capability, gaps in skills and training needs.
Systems such as Construction Line go some way to standardising and simplifying the tender process by allowing tenderers to provide pre-qualification information just once that can then be presented to multiple potential clients.
The government used to require public clients to use PAS 91, a standardised wording for pre-qualification questionnaires, however following the issue of (PPN) 03/24 it was clarified that PAS 91 is no longer actively supported (or updated) and that the Common Assessment Standard (CAS) is the preferred method for pre-qualification in public projects.
On July 1, 2024 Version 4 of the Common Assessment Standard (CAS) was published, including a new Building Safety section, ensuring it can be used to demonstrate companies have the organisational capability to fulfil their roles under the Building Safety Act. Below is a lists of the contents of Version 4 of the Common Assessment Standard issued in 2024 (with the previous headings from the 2023 version in brackets both the new and old versions cover 10 key areas;
- Section 1: Identity
- Section 2: Financial
- Section 3: Corporate and Professional Standing
- Section 4: Health and Safety
- Section 5: Environmental
- Section 6: Quality
- Section 7: Building Safety (previously Equality)
- Section 8: Fairness, Inclusion and Respect - FIR (previously Corporate Social Responsibility- CSR)
- Section 9: Information Security (previously Information Security and GDPR)
- Section 10: Information Management (IM)
In March 2021, a pre-qualification system went live. Developed by Build UK with support from the Civil Engineering Contractors Association, and endorsed by the Construction Leadership Council (CLC), the system has been adopted by contractors and clients including Balfour Beatty, Costain, HS2, Mace, Multiplex and Skanska. It is also supported by a number of leading trade associations, such as electrotechnical sector body ECA.
In December 2013, Enterprise Minister Matthew Hancock set out a range of measures intended to make it easier for small businesses to grow in Small Business: GREAT Ambition. Measures were announced to tackle late payment and to remove the barriers to public contracts by abolishing pre-qualification questionnaires (PQQs) for low-value contracts and mandating the use of core PQQs for high-value contracts.
For more information see article the common assessment standard.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Common assessment standard.
- Constructionline.
- Construction contract.
- ESPD and the decline of the PQQ.
- Expression of interest.
- Invitation to tender.
- Mid tender interview.
- PAS 91.
- Pre qualification questionnaires and PAS 91.
- Pre-qualification standard 2021.
- Pre tender interview.
- Procurement route.
- Selection criteria.
- Supplier assessment questionnaire.
- Tender documentation.
- Tender evaluation.
- Tender processes.
- The benefits of e-procurement in construction.
[edit] External references
- OGC Pre-Qualification Questionnaire for selecting suppliers.
- OGC PQQ.
- Construction Line.
- OGC Supplier Selection and Pre-Qualification: Guidance, tools and tips.
- OGC Pre-Qualification Questionnaire.
- Pre-qualification - PAS 91: the use of this standardised wording for PQQ's has been mandated within Government.
- PACE Guidance on the Appointment of Constractors and Consultants P480 Pre Selection Procedures.
Featured articles and news
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.