Pre-construction phase
The term ‘construction’ refers to the process of building something such as a house, bridge, tunnel, and so on.
Construction projects are typically divided up into stages, at the end of which the client assesses the state of development of the project and considers; whether it satisfies their strategic objectives, that it is affordable, that value is being delivered, and that risks are acceptable. They can then decide whether to progress to the next stage.
A typical project might follow stages such as:
- Stage 1: Business justification.
- Stage 2: Feasibility studies.
- Stage 3: Project brief.
- Stage 4: Concept design.
- Stage 5: Detailed design.
- Stage 6: Production information.
- Stage 7: Tender.
- Stage 8: Mobilisation.
- Stage 9: Construction.
- Stage 10: Occupation and defects liability period.
- Stage 11: Post occupancy evaluation.
Typically, the construction phase consists of carrying out the construction works described in the contract and preparing for the client to occupy the works.
The pre-construction works, in their broadest sense, might include any activities before the construction phase commences, such as; business planning, appointing consultants, the preparation of feasibility studies and options appraisals, preparing the project brief, designing the project, obtaining permissions, appointing a contractor, preparing for construction to commence and so on.
However, a specific legal meaning of “pre-construction phase” exists in relation to health and safety. The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced. They were introduced in 1994 following publication of European Directive 92/57/EEC on minimum safety and health standards for temporary or mobile construction sites.
The CDM Regulations 2015 suggests that the construction phase means the period of time beginning when construction work in a project starts and ending when construction work in that project is completed. The pre-construction phase refers to any period of time during which design or preparatory work is carried out for a project and may continue during the construction phase.
This might include:
- Appointing duty holders.
- Ensuring risks are eliminated or controlled through design work.
- Passing information to the principal contractor.
- Ensuring cooperation and coordination.
- Ensuring designers comply with their duties.
- Preparing pre-construction information.
For more information see: CDM 20215.
These activities may continue after the construction phase has commenced, as the design may continue to develop and so health and safety considerations may change.
NB Using Two Stage Open Book and Supply Chain Collaboration, published by HMSO in 2014, defines the preconstruction phase as: ‘…the phase of a project or programme of work before the Client authorises commencement of all works and related activities on and off site.’ It defines a preconstruction phase timetable as: ‘…a contractually binding timetable governing deadlines and interfaces for Preconstruction Phase activities by Integrated Team members under a Conditional Contract.’
[edit] Related articles on Designing Buildings
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.