Planning performance agreement
Planning performance agreements are voluntary undertakings that enable local planning authorities and applicants for planning permission to agree the timescales, actions and resources necessary to process a planning application. They are not intended to be legally-binding contracts, but are in the spirit of a ‘memorandum of understanding’.
They must be agreed before an application is submitted, and can cover the pre-application, application and post-application stages.
Planning performance agreements can be helpful in:
- Encouraging collaborative working between the applicant, the local planning authority, and third parties (where appropriate, third parties such as statutory consultees may be a party to the agreement).
- Establishing a transparent process for determining applications.
- Acting as focus for pre-application discussions.
They can be used for any application, but are particularly suited to large or complex applications. The structure of the agreement is determined by the local planning authority and the applicant, but depending on the complexity of the project may include:
- The status of the agreement.
- A shared vision.
- An agreed timetable.
- Development objectives.
- Responsibility for tasks.
- A programme for the negotiation of section 106 agreements and related non-planning consents.
- Voluntary payments to assist with any abnormal costs associated with processing the application.
Local planning authorities may charge for additional administrative work involved in the planning performance agreement.
The existence of a planning performance agreement means that the statutory time limits for determining the application no longer apply. If the local planning authority fails to determine the application by the agreed date, then the applicant may appeal, however, the agreement should be sufficiently flexible to allow for changes in circumstances.
The parties to the agreement are encouraged to make it publicly available.
[edit] Related articles on Designing Buildings Wiki
- Detailed planning application.
- Development management.
- Environmental impact assessment.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Neighbourhood planning.
- Outline planning application.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligations.
- Planning permission.
- Pre-application advice.
- Section 106 agreement.
- Statutory consultees.
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.