Named supplier in construction contracts
Naming suppliers allows the client to influence the main contractor's selection of suppliers, whilst leaving responsibility for their performance with the main contractor.
To name suppliers, the client first identifies a list of potential suppliers. They may invite these potential suppliers to submit tenders. The client then names a short-list of acceptable suppliers in the tender documents for the main construction contract. The tender documents allow for the named suppliers by including a provisional sum.
When tendering for the main contract, the main contractor makes allowances for mark up, attendance and programme in relation to the named suppliers. Once appointed, the successful contractor seeks tenders from the named suppliers (although they may reasonably object to any of them). If the client previously sought tenders form the named suppliers, they may pass these on to the main contractor, although it is the responsibility of the main contractor to negotiate an actual price.
Once the main contractor has selected and appointed a supplier, the provisional sum is replaced with the actual price agreed.
The main contractor pays the named supplier and the main contractor is responsible for their works. However, if the materials or goods supplied turn out not to be fit for purpose, then whoever named them will be responsible, not the contractor, unless the contractor was able to choose from a number of products available from the named supplier and they selected one that was unfit for purpose when others were available.
On public sector projects, a supply contract for which the client intends to provide a named list of possible suppliers may be subject to the requirements of the OJEU procurement rules.
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.