NEC4 contract creates a procurement alliance arrangement for all stakeholders
ICE’s collaborative NEC contract suite is the infrastructure procurement route of choice in the UK, Hong Kong, South Africa and New Zealand. In this article, Ian Heaphy introduces the latest member of the family, the NEC4 Alliance Contract. |
Contents |
[edit] Introduction
Following extensive industry consultation, ICE’s NEC division launched the NEC4 Alliance Contract (ALC) at the NEC Users’ Group annual seminar in London earlier this year.
The contract marks the next stage in NEC’s 25-year history of collaborative construction procurement and creates a ‘true’ alliance arrangement, where the client and all key members of the supply chain are engaged under a single set of conditions of contract.
All members of an ALC alliance have an equal voice and share in the performance of the alliance as a whole, as opposed to their own individual performance.
The contract is designed for use on major projects or programmes of work, where longer-term collaborative ways of working are to be created.
It can also be used to deliver a programme where a number of lower-value projects can be combined to create a major programme of work.
[edit] NEC approach to alliancing
All contracts in the NEC4 contract suite, which was launched in 2017, and their predecessors are collaborative in nature. They allow all key members of the supply chain to be engaged under contracts that contain the requirement at clause 10.2 for the parties to, "act in a spirit of mutual trust and co-operation".
Further collaboration can be achieved using secondary option X12 multi-party collaboration, which incentivises multiple suppliers to collaborate to achieve a common set of objectives set by the promotor (commonly the client).
ALC takes this further, building option X12 into the core of the contract.
Members of the alliance are thus required to collaborate with each other to achieve alliance objectives and individual member objectives. They work collectively to support delivery of the contract and establish an integrated alliance delivery team on a best-for-project basis.
[edit] Structure of the alliance
The client has a dual role in the ALC in that it has certain retained powers and functions that it performs outside of the alliance, as well as the power and functions of an alliance member.
An alliance board has overall responsibility for the alliance and sets strategy, appoints an alliance manager, makes decisions and resolves disputes.
Each alliance member has an alliance board representative, including the client.
The alliance manager manages the contract on behalf of the alliance and undertakes many of the functions exercised by the project manager or service manager under other NEC contracts, as well as some aspects of the contractor’s role.
Reflecting the collaborative nature of the contract, the majority of decisions of the alliance have to be made unanimously by the alliance board.
Alliance members share the majority of risk under the contract and agree that there can be no claims made against other members of the alliance except for very limited exceptions, principally due to a deliberate breach of contact.
[edit] Performance table
Payment by the client to other alliance members, which are referred to as partners, is on the basis of defined cost.
All partners are incentivised to achieve alliance objectives through a performance table, which sets out what performance is required and the reward or deduction regimes that apply if the performance targets are over- or under-achieved.
There’s already been considerable interest in the ALC from NEC users. The new contract also supports ICE’s Project 13 initiative to shift infrastructure procurement from transactions to enterprises.
This article is based on the author’s briefing article in the latest issue of the ICE Civil Engineering journal and originally appeared at: https://www.ice.org.uk/news-and-insight/the-civil-engineer/november-2018/new-nec4-contract-creates-true-alliance
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
- ICE articles on Designing Buildings Wiki.
- ICE Conditions of Contract.
- NEC contract change management systems.
- NEC contracts and collaborative working.
- NEC4 - legal and insurance aspects.
- NEC4 Alliance contract.
- NEC4 Design, Build and Operate Contract.
- NEC4.
- Partnering.
- Procurement route.
- Project 13.
- The Institution of Civil Engineers.
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.