NEC Option A: Priced contract with activity schedule
Contents |
[edit] What is NEC?
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It is now in its fourth edition, NEC4.
The Engineering and Construction Contract (ECC) is the most frequently used, and can be adopted on projects such as infrastructure, buildings, highways and process plants. It is used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
[edit] What is option A?
Option A is a priced contract with an activity schedule, which relates to a programme where each activity is allocated a price and interim payments are made against the completion of those activities. The contractor largely bears the risk of carrying out the work at the agreed prices.
The advantage of using an activity schedule is that it simplifies the administration of the interim payment process.
[edit] How are payments calculated?
The activity schedule on these types of project is submitted together with a contract programme as part of the tender.
The activity schedule is a more important document under Option A than under Option C, as it has a significant effect on the contractor’s cash flow by directly effecting the timing and payment amount.
The sum that is due to the contractor in each assessment period is defined as the total of:
- Each group of completed activities (those without defects).
- Each completed activity not in a group.
Only when the whole of an activity is complete does the payment become due to the contractor. There is no provision for part payment.
[edit] Related articles on Designing Buildings
- Activity schedule.
- Conditions of contract.
- Construction contract.
- Contract documents.
- Contractor's working schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- NEC Option F: Management contract.
- NEC3.
- Right to payment.
- Term contract.
Featured articles and news
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Stress Awareness Week ends but employer legal duties continue.
A call to follow the five Rs for the business and for the staff.
Key points and relevance to construction of meeting, due to reconvene.
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.