Joint and several liability in building design and construction contracts
In construction it is not unusual for more than one party to be responsible for a breach of contract. For example, there may be a design fault, a failure to inspect, and poor workmanship, all contributing to a defect in the works. Under common law (the Civil Liability (Contribution) Act 1978) all parties can be jointly and severally liable for the loss or damage that flows from the breach.
This means that the client can pursue the parties either jointly, or individually (severally) for the full amount of the loss. If the client decides to pursue one of the parties for the full amount, then that party may in turn pursue the other parties that contributed to the breach to recover their share of the amount claimed.
In practice, the claimant may decide to pursue the parties jointly, and allow the court to apportion liability between them (NB: This is not a matter of proportionate liability, which does not exist in English law, but is simply the apportionment of the full liability in contribution proceedings). However, 'several' liability can be of benefit to the client, if for example, the contractor becomes insolvent, allowing them to recover all of their losses from the remaining parties.
This can leave consultants and contractors open to very large claims, making them jointly and severally liable with parties that they did not themselves appoint, and whose performance they have little influence over.
The Latham report proposed that joint and several liability should be replaced by 'proportionate liability'. However, this was rejected by the Secretary of State for Trade and Industry Peter Mandelson. His position was endorsed by the British Property Federation (a body that represents the interests of construction clients).
The amount that can be recovered from one party can be limited by a net contribution clause. This restricts liability to the amount for which the party being pursued is responsible. Other amounts must be recovered from the other parties. Net contribution clauses assume that parties responsible for the same loss or damage are all contractually liable to the other party to the contract, and that they have paid the share that they would have been apportioned under common law.
Clients tend to resist net contribution clauses as they transfer the risk of not being able to recover losses onto the client. Whilst this is fair in that the client did appoint all the parties, the client themselves are completely innocent of the breach.
Net contribution clauses have become increasing popular in appointment agreements and collateral warranties. Questions remain however about whether they are always enforceable, for example where one of the parties to whom liability is apportioned is not present in court. However, in 2009, in the Scottish case of Langstane Housing Association v Riverside Construction (Aberdeen) Ltd, the court seemed to accept that this sort of clause was not unusual and that the client could, if they wanted, insure themselves against unrecoverable losses.
[edit] Related articles on Designing Buildings Wiki
- Causes of construction disputes.
- Civil procedure rules.
- Contract claims.
- Contribution and apportionment.
- Defects.
- Design liability.
- Latham report.
- Net contribution clauses.
- Loss and expense.
- Professional indemnity insurance.
- Strict liability.
[edit] External references
- Building: Latham's legacy.
- Joint and Several Liability in the Construction Industry: Is it time for law reform in the UK? (2004).
- Hugh James: Net Contribution Clauses in Construction Contracts - Are they fair and reasonable?
- Civil Liability (Contribution) Act.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.