Duress and undue influence
In law, a contract can be rendered null and void if one of the parties was not a free agent when they entered into it. This can occur if duress or undue influence was exerted on them when the contract was drawn up. It is then up to them to nullify the contract if they so wish.
A party to a contract may be coerced by:
- Violence.
- Threats of violence.
- Threats of criminal proceedings (even if this was just an empty threat).
- Having property seized.
- Similar threats applied to someone who is close enough to the party to the contract to make them feel the threat is to themselves. An example might be a threat to a next of kin or close friend which forces a party to sign a contract.
A contract is also voidable if one of the parties was influenced or guided by the other party, as may occur in parent/child, doctor/patient, trustee/beneficiary etc relationships. Where contracts have in such cases been entered into, the presumption is of undue influence by the stronger party on the weaker party who can therefore (and at their discretion) render the contract null and void. However, this can be refuted if it is established that the weaker party received independent legal advice before entering into the contract. The presumption of undue influence does not apply to husband/wife contracts.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
How orchards can influence planning and development.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.