Design and manage procurement route
Contents |
[edit] Introduction
The design and manage procurement route shares several characteristics of management contracting.
Under this arrangement, the works are constructed by a number of different works contractors who report to a management contractor who is selected early in the process. The management contractor assumes responsibility for the other contractors and the design team. This procurement approach is suitable for large, complex projects or fast track projects.
It may also be a preferred method when the client wishes to have one point of contact who is responsible for everything. A single point of contact is also the case with the design and build procurement route, although some clients feel this route is only appropriate for simple projects where design quality is not the first priority.
[edit] Variations
There are two common variations of the design and manage procurement route:
- The organisation is paid to design and manage the work and delivers the project by hiring subcontractors to design and construct the project.
- The organisation is paid as a consultant to act as the agent of the client to design and manage the work by obtaining subcontract tenders from works contractors who then each enter into a direct contract with the client.
[edit] Advantages and disadvantages
Potential benefits to the design and manage procurement route include:
- A collaborative relationship between the design and manage contractor and the client.
- Fewer delays caused by a lack of information or miscommunication.
- Clearer delineation of overall financial responsibilities for the default of sub-contractors.
Possible negative aspects of the design and manage procurement process include:
- The duplication of resources between trade contractors and the design and manage contractor, resulting in a higher prices.
- A lack of an established contract sum, resulting in an estimate created by the quantity surveyor and then endorsed by the design and manage contractor; it is then confirmed along the way as tendering progresses and the works proceed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.