Design and build - pros and cons
Design and build is a term describing a procurement route in which a single contractor is appointed to design (or complete the design) and then to construct the works. This is as opposed to a traditional contract, where the client appoints consultants to undertake the design and then a contractor is appointed to construct the works.
Design and build can be advantageous in terms of time as it allows the overlap of design and construction reducing the overall project delivery time.
The fact that there is a single point of responsibility for the client to deal with once the contract is awarded can also make things simpler. The client is also able to engage with the contractor and their design team or supply chain earlier in the design process to try and achieve a more practical or buildable solution if necessary.
In terms of cost, it allows the client a certain amount of control as the contractor generally agrees to take on responsibility for the design and construction for a pre-agreed price. This means that the contractor takes on much of the financial risk (which may be reflected in the price). However, as the contractor is responsible for the design, they may make cost savings here (which can impact on quality).
Under some design and build contracts, the design team will be novated to the contractor, which can benefit quality (ie they transfer from working for the client to working for the contractor). This can be beneficial to the client as it maintains continuity between pre-tender and post-tender design whilst leaving sole responsibility for designing and building the project with the contractor. However, it can leave them without suitable independent advisors to help them oversee the developing design and then the construction. For more information, see Novation.
There are some disadvantages to the design and build procurement route. In terms of quality, the contractor may exploit a specification that is open to interpretation and choose the cheapest route. This can mean that quality may be compromised if the employer’s requirements do not adequately ensure the anticipated specifications are adhered to.
There is also the risk that the client may have to pay more if the contractor has to take on an unreasonably high level of risk due to a lack of design clarity when tendering. In terms of design flexibility, it is also important to consider that any request for changes will have cost and time implications.
[edit] Related articles on Designing Buildings
- Construction contract.
- Construction management contract.
- Design and build.
- Design build operate (DBO).
- Design build operate maintain DBOM.
- Design liability.
- Employer’s requirements.
- JCT Design and Build Contract.
- Management contracting - pros and cons.
- Novation.
- Procurement route.
- Traditional contract - pros and cons.
Featured articles and news
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.























Comments