Design and build - pros and cons
Design and build is a term describing a procurement route in which a single contractor is appointed to design (or complete the design) and then to construct the works. This is as opposed to a traditional contract, where the client appoints consultants to undertake the design and then a contractor is appointed to construct the works.
Design and build can be advantageous in terms of time as it allows the overlap of design and construction reducing the overall project delivery time.
The fact that there is a single point of responsibility for the client to deal with once the contract is awarded can also make things simpler. The client is also able to engage with the contractor and their design team or supply chain earlier in the design process to try and achieve a more practical or buildable solution if necessary.
In terms of cost, it allows the client a certain amount of control as the contractor generally agrees to take on responsibility for the design and construction for a pre-agreed price. This means that the contractor takes on much of the financial risk (which may be reflected in the price). However, as the contractor is responsible for the design, they may make cost savings here (which can impact on quality).
Under some design and build contracts, the design team will be novated to the contractor, which can benefit quality (ie they transfer from working for the client to working for the contractor). This can be beneficial to the client as it maintains continuity between pre-tender and post-tender design whilst leaving sole responsibility for designing and building the project with the contractor. However, it can leave them without suitable independent advisors to help them oversee the developing design and then the construction. For more information, see Novation.
There are some disadvantages to the design and build procurement route. In terms of quality, the contractor may exploit a specification that is open to interpretation and choose the cheapest route. This can mean that quality may be compromised if the employer’s requirements do not adequately ensure the anticipated specifications are adhered to.
There is also the risk that the client may have to pay more if the contractor has to take on an unreasonably high level of risk due to a lack of design clarity when tendering. In terms of design flexibility, it is also important to consider that any request for changes will have cost and time implications.
[edit] Related articles on Designing Buildings
- Construction contract.
- Construction management contract.
- Design and build.
- Design build operate (DBO).
- Design build operate maintain DBOM.
- Design liability.
- Employer’s requirements.
- JCT Design and Build Contract.
- Management contracting - pros and cons.
- Novation.
- Procurement route.
- Traditional contract - pros and cons.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
Comments