Construction contract particulars
The contract particulars in a construction contract (or appointment agreement) set out the aspects of the contract that are particular to the project to which the contract relates. They are commonly found in standard forms of contract and are used to set out details that are at the discretion of the contracting parties, or identify the options that will be used from within the contract conditions, but without altering the overall intention of the contract clauses. Amending the conditions themselves might have unintended consequences.
These project-specific details are sometimes found in appendices to contracts, but are now commonly entered in a ‘contract particulars’ section at the beginning.
It is very important that the details in the contract particulars are filled in carefully, and the implications properly understood.
The nature and extent of the contract particulars will depend on the type and complexity of the agreement being entered into, however, they might include:
- The contract sum.
- The retention percentage.
- The interim payment period.
- Requirement for collaborative working.
- Requirement for early warning notification.
- Addresses for servicing notices.
- Nominees for negotiations.
- The details of the adjudicator / arbitrator or appointing body.
- Third party rights and collateral warranties.
- The contract base date.
- The completion date (or sectional completion dates).
- Details of key personnel.
- The date for possession.
- The maximum permitted period for the deferment of possession.
- Notice to proceed provisions (management contract)
- The amount of liquidated damages.
- The length of the defects liability period (or rectification period).
- The duration of the CDM planning period.
- Insurance requirements.
- Requirement to comply with the joint fire code.
- Net contribution clauses for sub-contractors.
- Permitted period for suspension of the works before the contract can be terminated.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Causes of construction disputes.
- Construction contract.
- Contract claims.
- Contract conditions.
- Housing Grants Construction and Regeneration Act.
- JCT.
- Modifying clauses in standard forms of construction contract.
- Procurement route.
- Scheme for Construction Contracts.
- Sub-contract.
Featured articles and news
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.