Conciliation in construction disputes
NB: ICE contracts have been withdrawn in favour of NEC contracts (Ref ICE) and the term ‘conciliation’ is gradually falling into disuse, regarded instead as a form of mediation.
Conciliation using the Institution of Civil Engineers’ Conciliation Procedure (1999) is a process that may be used at any time by agreement of parties who have contracted under the ICE family of contracts and associated subcontracts.
Once the parties have agreed to take part in the conciliation process, there is no right given under the ICE Procedure for a party to object to the appointed conciliator. Overall, the process set out in the Procedure gives very wide discretion to the conciliator as to how the conciliation is to be conducted; but, in practice, the process adopted is usually very similar to that for a typical mediation.
The principal difference between mediation and ICE conciliation arises when progress towards a settlement breaks down as, for example:
- when the conciliator is of the opinion that it is unlikely that a settlement will be achieved;
- a party fails to comply with some instruction of the conciliator; or
- either party indicates they do not wish to proceed towards a negotiated settlement.
In such circumstances the conciliator prepares a ‘recommendation’ which sets out their solution to the dispute. The various ICE contracts provide that if the conciliator makes a recommendation, and neither party dissents from that recommendation within one month of its issue by referring the dispute to adjudication or arbitration, then the recommendation becomes final and binding.
A similar situation applies when a dispute review board (sometimes referred to as a dispute resolution board DRB), appointed under the International Chamber of Commerce (ICC) Rules, issues a ‘recommendation’ with respect to any dispute referred to it. If no party expresses dissatisfaction with a recommendation within a stated time period, the parties contractually agree to comply with it.
If a party does express dissatisfaction with the recommendation within such time period, that party may submit the entire dispute to arbitration, if the parties have so agreed, or the courts. Pending a ruling by the arbitral tribunal or the court, the parties may voluntarily comply with the recommendation, but are not bound to do so.
This article was created by --University College of Estate Management (UCEM) 15:45, 11 December 2012 (UTC)
[edit] Related articles on Designing Buildings
- Alternative Dispute Resolution.
- Adjudication.
- Arbitration.
- Conciliator.
- Dispute resolution boards.
- How does arbitration work?
- Mediation.
- The role of the mediator.
[edit] External references
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February