Assignment of choses in action
Choses in action are ‘…all personal rights of property which can only be claimed or enforced by action and not by taking physical possession.’ (ref Torkington v Magee). The term includes the benefits arising under a contract and, subject to certain qualifications, rights of action arising by reason of a breach of contract.
A chose in action can be a legal chose, for example an interim payment due under a building contract, or an equitable chose such as a legacy under a will or an interest in a partnership.
Choses in action can be assigned or transferred unilaterally, for example A the employer enters into a construction contract with B the contractor, requiring B to construct a building to a quality set out in the specification. A can, without the consent of, or indeed knowledge of B, transfer the benefit of that contract to a third party C. A is known as the assignor, B the debtor and C the assignee. Only the benefits of a contract can be assigned, not the burdens (see Nokes v Doncaster Amalgamated Collieries). The burden must be novated.
It is important to understand that the right to assign a chose in action is not derived from contract. It is a statutory right, alternatively a right arising from the rules of equity. Express conditions are commonly found in collateral warranties purporting to grant rights of assignment; these conditions are unnecessary and may actually have the effect of restricting the rights to assign.
[edit] Related articles on Designing Buildings
Featured articles and news
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.