Alternative site assessment ASA
Contents |
[edit] Introduction
An Environmental Impact Assessment (EIA) ensures that the environmental effects of a proposed development are properly considered. For more information see: Environmental Impact Assessment. It provides the local planning authority with better information about certain types of projects, enabling them to make a more informed decision about whether permission should be granted and to allow imposition of more appropriate conditions and obligations to mitigate possible negative impacts.
It will typically include assessment of appropriate alternatives, including an alternative site assessment (ASA).
[edit] Purpose
The purpose of an ASA is to explore whether or not the site proposed for a development is the most suitable one, or whether alternative sites could be preferable.
Due to the impact they may have on the outcome of the planning process, it is important to have ASAs undertaken during the very early stages of a project - not as a process of post-rationalisation after a site has already been selected, and very early appraisals of potential sites may be carried out by a surveyor before the appointment of the consultant team during the business justification stage.
[edit] ASA guidance
There is no formally prescribed process or methodology for undertaking an ASA. The process should be adapted to the characteristics of different projects. However, the Surrey County Council offers suggested stages of an ASA, including:
[edit] Assessment of requirements
- Physical, including size of site and building requirements.
- Access, including distance to and from roads.
- Location, including desirability based on the existing or proposed area of operations.
- Relationships, including proximity to any existing/remaining premises, suppliers, markets.
[edit] Criteria for ASAs
- Whether the site is previously developed land or in active use for the proposed development.
- Likely visual impact.
- Standard of access.
- Likely impact on residential amenities.
- Distance from designated (i.e. environmentally sensitive) areas.
- Flood risk.
- Site availability (e.g. evidence of whether the site is listed for sale).
[edit] Related articles on Designing Buildings
Featured articles and news
Designing sustainability and performance into buildings
Specifying and selecting sustainable resilient timber products.
Modifying wood to improve resistance to decay and movement.
A last minute, long look for built environment professionals.
The architecture of creative reuse. Book review.
Installing solar panels on listed structures.
Sustainable development global goals, history in progress?
"Unless we act now, the 2030 Agenda will become an epitaph for a world that might have been."
Mike Kagioglou FCIOB named CIOB President
'Sustainable Development Goals must be focus for construction'
BSRIA training; a look at what's on offer
From energy management to compliance training.
TESP video warns to beware of rogue trainers.
Highlighting the slippery tactics of non-approved providers.
New Building Safety Wiki launched
Boosting awareness and understanding of the new fire safety regime.
New playbook on AI in construction published by CIOB
How to get to grips with, and the best from AI.
Digital Construction Report NBS
BIM, cloud, off-site, immersive tech, AI, twins and sustainability.
ECA learning zone and industry focus video series
From updates and amendments to circular economy, emergency lighting and much more.