Production information
The Construction Project Information Committee (CPIC) defines production information as '...the information prepared by designers, which is passed to a construction team to enable a project to be constructed'.
(Ref. CPIC The importance of production information - The Construction Project Information Committee provides best practice guidance on the preparation of production information.)
Production information is incorporated into tender documentation and then the contract documents.
The quality of production information is extremely important. Unless it is prepared and co-ordinated properly, there will be disputes and delays on site, and costs will be incurred.
Responsibility for production information depends on the selected system of procurement and the chosen form of contract.
On traditional contracts (and management contracts and construction management contracts), production information may be produced by the consultant team, on behalf of the client. Some elements of production information may be produced by specialist contractors, co-ordinated by the lead designer. Any gaps in this information that require specialist input after the tender process should be clearly defined showing abutment details to adjacent work faces and how such work is integrated into the overall scheme.
On other forms of contract (such as design and build or private finance initiative projects), responsibility for preparing production information and co-ordinating information prepared by specialist contractors may lie with the main contractor.
Production information may include:
- Drawings (location drawings, component drawings and dimensioned diagrams).
- Specifications, design criteria and calculations (specification information can be included on drawings or in a separate specification, but information should not be duplicated as this can become contradictory and may cause confusion).
- Bills of quantities or schedules of work (schedules of work are 'without quantities' instructional specifications often produced by designers on smaller projects for pricing, or for items such as builders work and fixing schedules, such as sanitary fittings, doors, windows, ironmongery, light fittings, louvers, roller shutters, diffusers, grilles and manholes).
There should be a particular emphasis on equipment with long manufacturing times, such as switchgear, chiller units, lifts, escalators or bespoke cladding systems, and on front-end construction such as service diversions, demolition, setting out details, underground drainage, piling and groundworks.
Definitions and rules relating to drawn information for 'with quantities' projects are described the New Rules of Measurement. See New Rules of Measurement for more information.
Increasingly, software is used to prepare elements of production information such as computer aided design (CAD) to prepare drawings, common data environments (CDE), and proprietary systems for the preparation of specifications.
The advent of building information modelling (BIM) can allow the automatic generation of all elements of production information from a single co-ordinated model, resulting in a reduction in errors and so costs.
[edit] Related articles on Designing Buildings
- Bills of quantities.
- Building information modelling.
- Common Arrangement of Work Sections (CAWS).
- Concept drawing.
- Construction drawing.
- Construction Project Information Committee.
- Elevations.
- New Rules of Measurement.
- Post-production information.
- Prescriptive specification.
- Procurement route.
- Production information report.
- Schedules of work.
- Shop drawings.
- Specifications.
- Standard Method of Measurement (SMM7).
- Work section.
- Working drawings.
[edit] External references
Featured articles and news
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.