Occupation and defects liability period
The process for completing the design and construction of a building is often divided into stages. This can be helpful in establishing milestones for the submission of progress reports, the preparation of information for approval, client gateways, and for making payments. However there is a great deal of ambiguity between the naming of stages by different organisations and the definition of what individual stages actually include (see comparison of work stages) and so it is important that appointment documents make it clear specifically what activities fall within which stage, and what level of detail is required.
Within the Designing Buildings Wiki project plans, the stage, ‘occupation and defects liability period’ follows practical completion. It is the stage after the client has taken possession of the development for occupation when any defects are rectified.
On large projects the contractor may set up a hot desk for responding to any complaints or to provide assistance required by the incoming occupants. As the development is now occupied, and the contractor no longer has possession of the site, close co-operation is required between the contractor and the client so as so not to disturb occupants, whose activities will take priority over work required to rectify defects. This may involve out of office hours working.
At the end of the defects liability period, the contract administrator arranges inspections of the works and prepares a schedule of remaining defects and agrees the programme for their rectification with the client and contractor. The contract administrator then arranges final inspections of the works and if satisfied issues the certificate of making good defects. A final report and final account will be prepared and the final certificate issued signifying that the construction works have been fully completed. Any remaining retention is released.
Issuing the final certificate will normally signify the end of the consultant teams appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
The occupation and defects liability period is analogous to the ‘Handover and close out’ stage of the RIBA Plan of Work, (See comparison of work stages), although the RIBA stage also includes post occupancy evaluation.
Within the Designing Buildings Wiki project plans post occupancy evaluation is part of the final stage ‘post occupancy evaluation’. This is the process of determining how successful the delivery of the project was, how successful the completed development is, where there is potential for further improvement, and what lessons can be learned for future projects. It can be particularly valuable to repeat developers and may be a requirement of some funding bodies. In practice, post occupancy evaluation may begin during the defects liability period, and ideally the client should commit to carrying out post occupancy evaluation at the beginning of the project so that appointments and briefing documents can include a requirement to test whether objectives were achieved.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.