Migration strategy
Once the client is certain that the project will proceed, they should appoint a senior director responsible for moving, who can stand their ground under pressure from various elements of management who may fight their corner during the stress and upheaval of moving. The job is one that requires the skillful co-ordination of a multitude of time consuming tasks. On larger projects this is likely to require a team of people working under the director, including an accommodation manager and perhaps a facilities manager.
After preparing a policy for occupation, setting out how the facility will be used (see article on occupation), the director and their team should prepare a migration strategy (or move in programme) setting out the procedures for moving in such a way as to minimise disruption whilst allowing the efficient re-use of assets from any existing facilities.
This migration strategy might include:
- A detailed, phased, logistical programme for purchasing or moving of furniture and equipment.
- A detailed, programme for moving or recruiting staff.
- Requirements for the hire of temporary equipment.
- Removal contracts.
- Setting up a help desk with a rapid response team.
- Postal and information and communications technology (ICT) arrangements to ensure continuity of communication (including transfer of hardware).
- Setting up 'goods in' and 'dispatch' rooms, a post room and an information and communications technology support centre.
- Catastrophe planning for fire or flood.
- Staff transportation strategy.
- Parking allocation.
- Access by consultants, contractors and suppliers for summer and winter checks of building services systems and environmental conditions (which can only be properly carried out in a fully operational building).
- Room allocation.
- Signage.
- Catering facilities and environmental health approval of kitchen areas.
- Liaison with emergency services.
- Stocking and storage of goods and consumables.
- Communications between facilities during the move.
- Installation of existing equipment requiring electrical, drainage, extract or cooling services such as vending machines or fume cupboards.
- A risk schedule with mitigation measures (for example; the absence of key personnel, late building handover, alarm activation, interruption of power or water supply and so on).
The client may also need to put procedures in place to move some of its staff and equipment so that it can continue to operate effectively during construction.
If the soft landings framework is adopted, there may be additional requirements to ensure a smooth transition from construction to occupation, and these should be included in appointment documents and contracts. See soft landings for more information.
[edit] Related articles on Designing Buildings
Featured articles and news
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.