Commissioning building systems
Commissioning refers to the process of bringing an item into operation and ensuring that it is in good working order. On building projects, this refers primarily to building services.
When, after all or part of a fixed building service or on-site electricity generation system has been installed, replaced or altered, the system is taken from a state of static completion to working order. Testing and adjusting are carried out for fixed building services, as necessary, to ensure that the whole system uses no more fuel and power than is reasonable in the circumstances. Testing and adjusting are carried out for on-site electricity generation systems, as necessary, to ensure that the whole system produces the maximum amount of electricity that is reasonable in the circumstances For each system, commissioning includes all of the following.
|
Building services requiring commissioning may include:
- Heating, cooling and ventilation systems.
- Generators.
- Switchboards.
- Water supply and sanitation.
- Pumps.
- Motors.
- Fire detection and protection systems.
- Information and communications technology (ICT) systems.
- Security systems.
- Facilities management systems.
- Process plant.
- Lifting equipment and escalators.
- Acoustic and vibration appraisals.
The contract documents should set out:
- Who will be responsible for commissioning different building services.
- What methods, standards and codes of practice are to be used.
- What should happen to test results.
- Whether commissioning is to be witnessed and if so, whom.
- The documentation that is required.
Commissioning can benefit from the preparation of a commissioning plan, which according to BSRIA Guide BG 8/2009 Model Commissioning Plan should:
- Provide general information about the project.
- Identify the commissioning team members for each stage of the commissioning process.
- Define roles and responsibilities for each commissioning team member.
- Identify the systems to be commissioned.
- Create a schedule of commissioning activities for each stage of the process.
- Establish documentation requirements associated with the commissioning process.
A commissioning manager may be appointed to give advice during design, construction planning and installation and then to manage commissioning, testing and handover.
Commissioning activities may include:
- Ensuring client access and providing client training and demonstrations.
- Completing operating and maintenance manuals, record drawings, software and test certification.
- Obtaining statutory approvals and insurance approvals.
- Manufacturers work testing.
- Component testing.
- Pre-commissioning tests.
- Set to work: this is the process of switching on (i.e. setting to work) items such as fans and motors to ensure that they are operating as specified (for example checking that fans are turning the right way).
- Balancing: this follows setting to work and involves looking at whole systems (rather than individual components) to ensure that they are properly balanced (i.e. water is coming out of all the taps at the correct pressure, air is coming out of the correct diffusers, etc).
- Commissioning checks and performance testing.
- Post commissioning checks and fine tuning during occupancy.
NB: The building regulations require that a commissioning notice is given to the relevant building control body (BCB) confirming that commissioning has been carried out according to a procedure approved by the Secretary of State. See Commissioning notice for more information.
Commissioning Air Systems (BG 49/2015), written by Chris Parsloe and published by BSRIA in March 2015, defines commissioning as: ‘The advancement of an installation from the state of static completion to full working order to specified requirements. For air systems, it includes the setting to work of an installation and the regulation of flow rates.’
[edit] Related articles on Designing Buildings
- BREEAM seasonal commissioning.
- BSRIA Water Treatment for Closed Heating and Cooling Systems BG 50/2021.
- Client commissioning.
- Commissioning documents.
- Commissioning notice.
- Commissioning plan.
- Commissioning planning.
- Commissioning report.
- Commissioning v testing.
- Corrosion in heating and cooling systems.
- Handover to client.
- IAQ developments accelerated by COVID-19 pandemic.
- Initial commissioning case studies.
- Inspection.
- Migration strategy.
- Practical completion.
- Seasonal and continuous commissioning.
- Soft landings.
- Specialist commissioning manager.
- Training for pre-commissioning cleaning of pipework systems.
Featured articles and news
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Comments