Thermal storage for cooling
Contents |
[edit] Introduction
Ice can be used as an effective means of thermal storage, storing ‘coolth’ in colder parts of the day to provide cooling during warmer parts of the day. Thermal storage for cooling can be a useful way of achieving efficiency and carbon emission reductions in climates with wide daily temperature variations, especially in areas where water is not available for heat rejection. It can also be a useful way of gaining utility incentives and reducing peak demand charges.
[edit] Design considerations
For ice storage systems, the heat absorption rate of the system is reduced as more of the ice is melted. The capacity of the system should factor in when the peak heat absorption rate is required as the stored energy is used. It may not be detailed enough to integrate the load profile over the period for which storage will be used and size the system on that alone. The storage system may end up undersized as a result.
Chillers that will be used to build ice as well as directly cool loads should be specified with electronic expansion valves rather than mechanical thermal expansion valves to enable easy switching between evaporator temperature set points. This is a bigger issue with smaller, non-VFD chillers (variable frequency drive) and modular chillers where a TXV (thermal expansion valve) will be the standard.
Wet bulb temperatures vary over a narrower range than dry bulb temperatures so with water-cooled systems the carbon benefits are seen on the electric utility side where efficient base load powerplants shoulder a higher load than inefficient "peaking" power plants.
Ice storage is not applicable to absorbers. Ice storage may however be applied in parallel with absorbers. Chilled water storage may be applicable to absorbers which are waste heat fired absorbers. Solar fired absorbers are probably not the best application for storage unless a design were to be considered without any other refrigeration technology. It might be more efficient to store the excess energy in such a system as heated fluid before it is used by the absorbers.
[edit] Ice storage sizing
The total installed chiller capacity (both glycol and conventional) for an ice system should be around 65% of the total peak cooling load. This will however depend entirely on the load profile. The purpose of using conventional chillers is to meet the base load ie the consistent load that exists right through the night, this also simplifies control as there is no simultaneous ice building and direct cooling. An example of a load profile is shown below.
The blue represents the baseload chiller. The nature of the buildings means that the night time load is a very small percentage of the peak load and so in this case, there is only one conventional baseload chiller rated at 3900kW. The purple/mauve colour represents the glycol (ice) chillers in charging mode, building ice. The light blue represents the glycol chillers operating in direct cool mode, the dark blue is then the ice being harvested to meet the peak load.
In this case, there were four ice chillers each at around 3800kW arranged in modules, which is how they achieve the simultaneous cooling and ice building at 0:00. Thus the ice chillers ran during the day; the glycol did not affect the COP (coefficient of performance) too much as they ran at normal temperatures during the day. The capacity was derated due to the heat transfer reduction of the glycol, but the actual efficiency may only have reduced by about 10%. When they reduced to operate in night mode the output was always derated, usually around 60% but the efficiency again was still good because of the cooler night time temperatures.
The split between baseload and ice chillers is highly dependent upon load profile but it will range typically from around 25-50% baseload chiller. For a 24 hour operating building it will be closer to 50%.
In terms of overall energy savings, they are most effective when using air cooled chillers when there is a peak diurnal range of at least 10°C. Another good way to improve efficiency is to harness a large delta T; use the chillers to precool the water at a higher than usual temperature 15-8° and then go through ice to go from 8-3. This means that the chiller operates at more favourable conditions. Then consider the operating savings connected to fans and pumps. This means the overall savings are not easy to predict without a significant amount of detail, but with air cooled chillers there will be savings.
All of this assumes the use of a peak lopping system which gives optimum capital expenditure (capex). Using a full storage system is more efficient as all cooling occurs at night but the capex is much higher as there will generally need to be more chillers than a conventional system in addition to the ice.
Finally in terms of space, ice storage systems don’t save huge amounts on the central plant, the ice tanks do need space but the chiller farm size is reduced (which would be difficult to hide architecturally). This is particularly true for large air-cooled plants. There are then space savings from the large delta T and low temperature which reduces ducts/pipes and airhandling plant.
This article was created by --Buro Happold.
[edit] Related articles on Designing Buildings Wiki
- Dynamic thermal modelling of closed loop geothermal heat pump systems.
- Earth-to-air heat exchangers.
- Geothermal energy.
- Geothermal pile foundations.
- Ground energy options.
- Ground pre-conditioning of supply air.
- Ground source heat pumps.
- Night-time purging.
- Phase change materials.
- Thermal labyrinths.
- Thermal mass.
- Thermal storage for cooling.
[edit] External references
- Calmac http://www.calmac.com/
- Cryogel http://www.cryogel.com/
- Balitomore Air Coil http://www.baltimoreaircoil.com/
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.