Conciliation in construction disputes
NB: ICE contracts have been withdrawn in favour of NEC contracts (Ref ICE) and the term ‘conciliation’ is gradually falling into disuse, regarded instead as a form of mediation.
Conciliation using the Institution of Civil Engineers’ Conciliation Procedure (1999) is a process that may be used at any time by agreement of parties who have contracted under the ICE family of contracts and associated subcontracts.
Once the parties have agreed to take part in the conciliation process, there is no right given under the ICE Procedure for a party to object to the appointed conciliator. Overall, the process set out in the Procedure gives very wide discretion to the conciliator as to how the conciliation is to be conducted; but, in practice, the process adopted is usually very similar to that for a typical mediation.
The principal difference between mediation and ICE conciliation arises when progress towards a settlement breaks down as, for example:
- when the conciliator is of the opinion that it is unlikely that a settlement will be achieved;
- a party fails to comply with some instruction of the conciliator; or
- either party indicates they do not wish to proceed towards a negotiated settlement.
In such circumstances the conciliator prepares a ‘recommendation’ which sets out their solution to the dispute. The various ICE contracts provide that if the conciliator makes a recommendation, and neither party dissents from that recommendation within one month of its issue by referring the dispute to adjudication or arbitration, then the recommendation becomes final and binding.
A similar situation applies when a dispute review board (sometimes referred to as a dispute resolution board DRB), appointed under the International Chamber of Commerce (ICC) Rules, issues a ‘recommendation’ with respect to any dispute referred to it. If no party expresses dissatisfaction with a recommendation within a stated time period, the parties contractually agree to comply with it.
If a party does express dissatisfaction with the recommendation within such time period, that party may submit the entire dispute to arbitration, if the parties have so agreed, or the courts. Pending a ruling by the arbitral tribunal or the court, the parties may voluntarily comply with the recommendation, but are not bound to do so.
This article was created by --University College of Estate Management (UCEM) 15:45, 11 December 2012 (UTC)
[edit] Related articles on Designing Buildings
- Alternative Dispute Resolution.
- Adjudication.
- Arbitration.
- Conciliator.
- Dispute resolution boards.
- How does arbitration work?
- Mediation.
- The role of the mediator.
[edit] External references
Featured articles and news
BSRIA Briefing 2024: Sustainable Futures speakers
Redefining Retrofit for Net Zero Living 22 Nov.
Wall of support for post-Grenfell regulation of electricians
Call for a shake-up of the construction industry highlighted on radio.
Digital sustainability through future AEC tools
Bringing together industry and academia to meet challenges.
Skills gap for net zero highlighted to Minister for Industry
ECA convenes roundtable discussion at Portcullis House.
Evidencing Net Zero with the new UK buildings standard
Pilot version with detailed excel proforma out now!
Scottish Building Safety Levy, in consultation
From direct remediation and the RPDT, to the costs and alternatives.
Waves of warmer homes grants for the rental sector
Boosting energy efficiency standards for all rented homes.
A refocus of the National Planning Policy Framework
Key terms described in brief, as the consultation closes the evening of the 24th.
Fortified farmhouses of the unruly 16th-and 17th-century borders.
ECA shares advice for those who may be exposed to risks.
How to revolutionise UK housing with MMC
CIC and Supply Chain Sustainability School unveil a plan.
From the UKs largest manufacturer and supplier of lime.
From mud bricks to smart concrete
A brief history from 7000BC to a future on the moon.
Regulator of Social Housing publishes latest fire safety report
Covering remediation of 11 metre plus social housing sector buildings.
Apartment and Duplex Defects Remediation Bill 2024
Approved for priority drafting by Government of Ireland.
The long list with in the frame of key historical events.
Competence frameworks for sustainability in the built environment
Code of practice, core criteria consultation draft for comment.
New Floods Resilience Taskforce
With a wet met office autumn prediction.