Shadow tolls
![]() |
A portion of the A1(M) is funded through shadow tolls. This is the Peterborough services sign. |
Contents |
[edit] Introduction
Shadow tolls are a funding mechanism sometimes used for public private partnership (PPP) projects paid for through private finance initiatives (PFI). Private finance initiatives are a form of PPP that is sometimes used for central civil government projects.
A shadow toll is an arrangement between a public client and private contractor in which the tolls or fees are paid directly to the contractor. This arrangement tends to last from 20 to 30 years beyond the construction completion date of the project.
[edit] History
Shadow tolls are widely used in the UK. They were originally proposed by the Government in 1993. In 2012, the Prime Minister David Cameron mentioned shadow tolls as a method for funding additional road construction. Since that time, this funding method has become less popular for PFI projects. This may be partially due to the increasing use of - and preference for - performance-based availability payment funding options. In addition, PFI has been widely discredited as an efficient procurement route. For more information see: Private Finance Initiative.
[edit] Flexible financing
Under a shadow toll arrangement, the public sector client pays the contractor a specific amount that is taken from the tolls collected for the use of the highway, bridge, tunnel, roadwork or other built. If, for whatever reason, there are no tolls exacted on the project, the client pays the contractor a pre-arranged fee, which is sometimes based on a per-vehicle amount. In either instance, the shadow tolls serve as the basis for compensation paid for operating and maintaining the project.
The public and private entities whose assets increase in value - due to potential business generated by the traffic - may pay a portion of the financing through tolls to the owner or operator of the asset. This incoming revenue can sometimes be used in place of direct tolls collected from those who drive their vehicles on the road.
This diversification of revenue adds to the appeal of shadow toll arrangements, since they can attract several funding sources. They can also distribute benefits across these funding sources.
Shadow tolls have been commonly used for large infrastructure projects that are structured according to design-build-finance-operate-maintain (DBFOM), design-build-finance-maintain (DBFM) or design-build-finance-operate (DBFO) procurement routes.
[edit] PPPs and shadow tolls
PPPs are a very broad range of partnership in which the public and private sectors collaborate for some mutual benefit. They were first developed in the UK in the 1990s in the belief that private sector companies might be more efficient at providing certain services than public authorities and so could deliver better value for money for taxpayers.
PPPs can cover a range of partnerships to deliver infrastructure construction, renewal and maintenance. Partnerships can be arrangements made either with central or local government entities. For PPP projects, risk for designing, building (sometimes financing), maintaining and operating an asset are shared by both the client and the contractor.
[edit] Shadow tolls in the UK
Some shadow toll schemes in the United Kingdom are structured so the fee payments to the client decrease if the traffic increases. This strategy is meant to drive demand for usage of the road rather than the number of vehicles carried, motivating the contractor to provide a well performing asset that meets a desirable level of service.
Congestion charging serves as a form of shadow toll. Its purpose is not to increase traffic. Instead, it is meant to create a roadway system that moves freely where cars can travel safely. The significance of this variety of shadow tolls is that it removes the need to tie payments to usage and shifts the risk associated with demand back to the client.
Shadow toll roadway projects in the UK include:
- M1 Lofthouse to Bramham link road
- M40 Denham to Warwick
- M80 Stepps to Haggs
- A1 Darrington to Dishforth
- A1(M) Alconbury to Peterborough
- A13 Limehouse to Wennington (Greater London)
- A19 Dishforth to Tyne Tunnel
- A249 Stockbury (M2) to Sheerness
- A30 Exeter to Bere Regis]
- A417 Gloucester to Cirencest
- A419 Swindon to Cirencester
- A50 Stoke to Derby link
- A69 Carlisle to Newcastle
[edit] Case study: Dulles Greenway
In the state of Virginia, the Dulles Greenway is a 14-mile shadow toll highway project that was privately financed and constructed between 1993 and 1995. The initial agreement reverts operational responsibilities back to the state in 2036.
To finance the Greenway, funding was obtained through loans that were to be repaid with toll revenues. However, a lack of traffic failed to generate the projected amount, so tolls - and legal speed limits - were increased on the road to entice drivers to use the highway. Revenue continued to miss targets, prompting the state to renegotiate a 20 year extension to the original agreement.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February