Pirelli General Cable Works Ltd v Oscar Faber & Partners
The case of Pirelli General Cable Works Ltd v Oscar Faber & Partners [1983] has been used as precedent for the limitation period applicable to claims of negligent design.
Damage to a factory arose out of the use of a material in constructing a factory chimney that was unsuitable for the purpose. The chimney had been built in 1969 but the faulty condition of the chimney could not have been discovered with reasonable diligence until 1972 and was not in fact discovered until 1977. A writ was issued in 1978. The question was whether the six year period ran from the date the faulty chimney was built or from the date when the fault could have been or was discovered. |
https://publications.parliament.uk/pa/ld200506/ldjudgmt/jd060301/haward-2.htm |
The House of Lords held that the owner of a building had a legitimate cause of action against the consulting engineer for a negligent design at the point at which physical damage to the building first occurred.
The subsequent case of Abbott v Will Gannon & Smith Ltd [2005] challenged the Pirelli law at the Court of Appeal on the basis that the case of Murphy v Brentwood DC [1991] decided that the cause of action accrued, not when physical damage first occurred but when the building owner suffered economic loss.
The Court held that the Murphy decision had not expressly or impliedly overruled the Pirelli decision. It held that if the claimant’s cause of action accrued at the time they suffered economic loss, then the loss only occurred when it became apparent in some way which would affect the building’s value. Therefore, they rejected the argument that economic loss was suffered when negligent works were completed.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February