Pirelli General Cable Works Ltd v Oscar Faber & Partners
The case of Pirelli General Cable Works Ltd v Oscar Faber & Partners [1983] has been used as precedent for the limitation period applicable to claims of negligent design.
Damage to a factory arose out of the use of a material in constructing a factory chimney that was unsuitable for the purpose. The chimney had been built in 1969 but the faulty condition of the chimney could not have been discovered with reasonable diligence until 1972 and was not in fact discovered until 1977. A writ was issued in 1978. The question was whether the six year period ran from the date the faulty chimney was built or from the date when the fault could have been or was discovered. |
https://publications.parliament.uk/pa/ld200506/ldjudgmt/jd060301/haward-2.htm |
The House of Lords held that the owner of a building had a legitimate cause of action against the consulting engineer for a negligent design at the point at which physical damage to the building first occurred.
The subsequent case of Abbott v Will Gannon & Smith Ltd [2005] challenged the Pirelli law at the Court of Appeal on the basis that the case of Murphy v Brentwood DC [1991] decided that the cause of action accrued, not when physical damage first occurred but when the building owner suffered economic loss.
The Court held that the Murphy decision had not expressly or impliedly overruled the Pirelli decision. It held that if the claimant’s cause of action accrued at the time they suffered economic loss, then the loss only occurred when it became apparent in some way which would affect the building’s value. Therefore, they rejected the argument that economic loss was suffered when negligent works were completed.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.