Non-compliant tender
This article describes in detail the tender process for a typical commercial construction contract.
For a wider description of the range of tender processes that might be adopted on different types of project, see Tender processes.
For more information about different contractual procurement routes, see Procurement route.
An invitation to tender will generally include very specific requirements for the information and format of the tender that prospective suppliers must submit. This ensures that necessary information is included and that it is in a format that the client is able to analyse and compare with other tenders.
If a prospective contractor or supplier submits a tender that does not comply with the client's requirements then that bidder is said to have submitted a non-compliant bid. This can result in the tender being rejected. Full compliance requires that all material conditions of the invitation to tender must be complied with.
A tender may be non-compliant by:
- Not answering all the question(s).
- Exceeding the required word length.
- Submitting in the wrong format e.g PDF when Excel or Word were required.
- Making a late submission.
- Not breaking down information in the correct way.
- Submitting proposals that do not comply with the client's requirements.
However, a non-compliant proposal, sometimes referred to as a variant bid, may be submitted intentionally if the tenderer believes that an alternative could offer better value for money that the requirements set out in the invitation to tender. However, non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they may need to be accompanied by a compliant bid to allow direct comparison with other tenders.
See also: Qualified bid.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Bid writer.
- Competitive tender.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Qualified bid.
- Selection criteria.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Refurbishment for net zero; the BSRIA white paper
The everyday practice of tackling energy efficiency, fabric first, ventilation, air quality, and occupant wellbeing.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Stress Awareness Week ends but employer legal duties continue.
A call to follow the five Rs for the business and for the staff.
Key points and relevance to construction of meeting, due to reconvene.
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.