Midland Expressway Ltd v Carillion Construction Ltd & Others
The case of Midland Expressway Ltd. v Carillion Construction Ltd., Alfred MacAlpine Construction Ltd., Balfour Beatty Group Ltd., AMEC Capital Projects Ltd., John E. Price (No.2) [2005] concerned the new M6 toll road construction near Birmingham and is important with regard to Private Finance Initiatives (PFIs) and Public Private Partnerships (PPPs).
The four defendant contractors worked together as a joint venture called CAMBBA. A concession agreement was granted in 1992 by the Secretary of State to Midland Expressway Ltd. (MEL) for them to design, construct and operate the M6 Toll Road. MEL and CAMBBA entered into a design and construct sub-contract in 2000.
‘Equivalent project relief’ provisions were contained within the sub-contract which limited the sub-contractor’s (CAMBBA) right to payment for variations and delay to the amount that MEL was able to recover from the Secretary of State. A mechanism that was intended to ensure this in the sub-contract restricted the subcontractor’s right to adjudicate an issue until a relevant adjudication had been brought between MEL and the Secretary of State.
As a result of variations, CAMBBA made claims for additional payment which, when they were disputed, CAMBBA wished to refer to adjudication. In response, MEL applied for a declaration and injunction preventing them from referring the claim to adjudication, arguing that the sub-contract did not provide them with any jurisdiction. The correct dispute, according to MEL, was between the Secretary of State and CAMBBA, as they were only a conduit between them.
CAMBBA argued that the ‘equivalent project relief’ and adjudication provisions in the subcontract cut across the statutory entitlement under the Housing Grants, Construction and Regeneration Act (HGCRA). Section 108 states that a subcontractor is entitled to commence an adjudication ‘at any time’. As the design and construct contract was a legitimate ‘contract’ under HGCRA, the dispute could be referred to adjudication.
The Technology and Construction Court (TCC) agreed with CAMBBA, and it was held that the adjudication provisions in the sub-contract were invalid. The ‘pay when paid’ aspect of the ‘equivalent project relief’ provisions was viewed as infringing section 113 of HGCRA which sought to guard against such clauses. Therefore, CAMBBA did not have to wait to be able to refer the dispute to adjudication.
Since previously, ‘equivalent project relief’ provisions had ensured that contractors were able to act as conduits for subcontractor claims without having liability, the repercussions of the case were that limiting the right to adjudication could no longer be used as a mechanism for meeting that objective.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February