Health and safety plan
The requirement for a Health and Safety Plan for construction was established by the Construction (Design and Management) Regulations (or 'CDM Regulations') in 1994. The regulations came into force on 31 March 1995.
The regulations were introduced to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced.
The original regulations required that the Planning Supervisor ensure a Pre-Tender Health and Safety Plan was prepared for contractors setting out:
- A general description of the construction work.
- The programme.
- Risks to the health or safety of any person carrying out the construction work.
- Other information enabling the contractors to demonstrate the competence and adequacy of resources.
- Other information enabling the contractors to understand and perform their duties under the regulations.
The Principal Contractor then ensured that during the construction phase the Health and Safety Plan contained information about:
- Arrangements for the project to ensure the health and safety of all persons carrying out the construction work and all persons who may be affected by the work.
- Information about arrangements for the welfare of persons carrying out the construction work.
However, the CDM Regulations were substantially revised in 2007. Amongst many changes:
- The role of Planning Supervisor was replaced with a new, more hands-on CDM Co-ordinator.
- The Pre-Tender Health and Safety Plan was replaced with Pre-Construction Information, provided by the client and checked by the CDM Co-ordinator.
- The Health and Safety Plan was renamed the Construction Phase Plan (CPP), developed by the Principal Contractor.
NB: Rather confusingly, the Construction Phase Plan is still sometimes referred to as the Construction Phase Health and Safety Plan.
[edit] Related articles on Designing Buildings Wiki
- Automated external defibrillator AED.
- CDM.
- CDM Co-ordinator.
- Construction phase plan.
- Emergency plan.
- Health and safety file.
- Planning supervisor.
- Pre-construction information.
- Principal contractor.
- Safety.
- Safety audit.
[edit] External references
Six things to include in the health and safety plan for a construction site
Featured articles and news
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
Comments
Out of date information - CDM regulations updated in 2015