Health and safety plan
The requirement for a Health and Safety Plan for construction was established by the Construction (Design and Management) Regulations (or 'CDM Regulations') in 1994. The regulations came into force on 31 March 1995.
The regulations were introduced to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced.
The original regulations required that the Planning Supervisor ensure a Pre-Tender Health and Safety Plan was prepared for contractors setting out:
- A general description of the construction work.
- The programme.
- Risks to the health or safety of any person carrying out the construction work.
- Other information enabling the contractors to demonstrate the competence and adequacy of resources.
- Other information enabling the contractors to understand and perform their duties under the regulations.
The Principal Contractor then ensured that during the construction phase the Health and Safety Plan contained information about:
- Arrangements for the project to ensure the health and safety of all persons carrying out the construction work and all persons who may be affected by the work.
- Information about arrangements for the welfare of persons carrying out the construction work.
However, the CDM Regulations were substantially revised in 2007. Amongst many changes:
- The role of Planning Supervisor was replaced with a new, more hands-on CDM Co-ordinator.
- The Pre-Tender Health and Safety Plan was replaced with Pre-Construction Information, provided by the client and checked by the CDM Co-ordinator.
- The Health and Safety Plan was renamed the Construction Phase Plan (CPP), developed by the Principal Contractor.
NB: Rather confusingly, the Construction Phase Plan is still sometimes referred to as the Construction Phase Health and Safety Plan.
[edit] Related articles on Designing Buildings Wiki
- Automated external defibrillator AED.
- CDM.
- CDM Co-ordinator.
- Construction phase plan.
- Emergency plan.
- Health and safety file.
- Planning supervisor.
- Pre-construction information.
- Principal contractor.
- Safety.
- Safety audit.
[edit] External references
Six things to include in the health and safety plan for a construction site
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Comments
Out of date information - CDM regulations updated in 2015