Early appointment / involvement
Contents |
[edit] Introduction
Early appointment typically refers to the involvement at the earliest possible stage in the design process of certain stakeholders to a construction project, with the aim of fostering partnering and improved team working. This will help ensure a project environment that manages risk, encourages innovation, improves collaboration, is less adversarial, and minimises unforeseen costs and delays – all of which can help deliver value for money.
[edit] Contractor
Early contractor involvement (ECI) allows contractors to participate in both the design development and construction planning stages. This can be essential for some projects, especially very large or complex projects and particularly those that rely on building information modelling (BIM), or where speed it important.
ECI clauses are now part of NEC contracts which are published by the Institution of Civil Engineers (ICE). A single NEC3 Engineering and Construction Contract (ECC) can be used for both stages where contractors are participating. ICE has suggested that early contractor involvement “...supports improved team working, innovation and planning to deliver value for money”.
ECI allows the contractor to input contractual, construction and design experience and ideas at an early stage in consultation with the client, architect, engineer and other consultants. In so doing, the contractor can influence the design in a beneficial way, advise on constructability, cost estimating, in-use performance, construction sequencing, materials and lead times, site considerations and a host of other matters that the client and other consultants may not have as much experience of. This means the contractor becomes familiar with the project over a longer period of time and can help avoid costly mistakes and delays.
The client (or employer) can appoint the contractor to help its consultants with the project design or to design specific elements. This is normally followed by the contractor being asked to deliver the works. Alternatively, the client can appoint the contractor to deliver the design helped by the client’s consultants.
For more information see: Early contractor involvement.
[edit] Key sub-contractors and suppliers
Early involvement of key sub-contractors and suppliers in the design process can also have benefits for a project such as establishing market pricing for the work involved, contributing to the design process, developing long lead time items and so on. This can also help the client, sub-contractors, suppliers and main contractor mitigate risk.
[edit] Other stakeholders
Community ‘buy-in’ (local residents, businesses, politicians and community groups and so on) at an early stage in a construction project can result in benefits for a project. Informed stakeholders that are part of the dialogue can enhance a project, avoiding potentially disruptive community relations and bad publicity. An involved community will more likely lend its support to a project.
Educating the community about a project’s goals is based primarily on providing information and inviting dialogue at workshops, meetings and other events which:
- Allow the community to generate ideas for project planning and implementation;
- Helps establish project sustainability and discovers what the community thinks and needs;
- Improves community relations and
- Gives the community a sense of empowerment that fosters acceptance.
For more information see: Stakeholder management.
[edit] Related articles on Designing Buildings Wiki
- Collaborative practices.
- Construction contract.
- Contract conditions.
- Contractor's design portion.
- Defined cost.
- Delay damages.
- Early contractor involvement.
- Institution of Civil Engineers.
- JCT.
- Latham Report
- Management contract.
- NEC contract change management systems.
- NEC3.
- Optimised contractor involvement.
- Procurement route.
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.