1 and 2 New Ludgate
Article from the June 2015 edition of the CIBSE Journal written by Phil Thompson.
Limited space and strict noise requirements led to a compact, enclosed chiller being specified for an office scheme at 1 and 2 New Ludgate, in central London.
The strict noise requirements of Land Securities’ commercial development helped to determine the specification of the chillers for the project. Air conditioning manufacturer Carrier worked closely with the client, consultant and contractor, SRW, to develop a compact, energy efficient design that enabled the chillers to be located in a restricted space. As a result, the chillers could be mounted on the rooftop, rather than in the basement, which was where the plant was located in the original design. This gave Land Securities more usable commercial space.
The chiller manufacturer designed and built a custom package to enclose the chillers and reduce the amount of noise. The condensers are specifically configured to resist damage from hailstorms that can otherwise create significant, accumulating, impact damage to the coils, reducing their performance.
Air conditioning for the buildings is supplied by six 930 kW (nominal) chillers with variable speed drive (VSD)-controlled screw compressors, alongside six smaller chillers with scroll compressors. The project included a bespoke pump, control and chiller sequencing package.
"The software was programmed in-house and designed to maximise energy efficiency and air conditioning performance, as well as extend the working life of the chillers by careful run-time sequencing," says Danny Lear, specification and solutions manager at Carrier UK. "We were able to carry out full witness testing of working chillers at our facility in France, ensuring the solution met the specification fully."
After installation, Carrier’s service team will, under a full-maintenance contract, ensure the chillers are maintained at peak performance level. The six screw compressor chillers are supplied with integral control that combines variable-speed condenser fans with variable-speed screw compressors, enabling close matching of cooling output to current load conditions. The constant control of the onboard intelligent control system, claims Carrier, enables the chiller to operate with very good part-load efficiency.
With the ability to vary both condenser fan speed and compressor speed in response to constantly changing demand, the chiller can continue to operate in its ‘sweet spot’ in terms of performance and energy efficiency. Carrier asserts it delivers a full-load energy efficiency ratio (EER) of up to 3.4 and a European seasonal energy efficiency ratio (ESEER) up to 4.9. Through a control system, building owners can monitor log performance data from the chiller via a web browser.
Newly introduced software optimises the use of compressors, fans and cooling circuits by constantly calculating the most efficient fan speed and water-flow rate, based on the current load and ambient conditions, and controls them to main appropriate refrigerant operating pressures through continuous feedback and adjustment.
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.