Builder's work in connection
The term ‘builder’s work in connection’ (BWIC) refers to builder's work that is necessary as a result of other works, typically mechanical and electrical services but also specialist installations, such as lifts, escalators, roller shutters, hoists and cleaning cradles, and so on.
For example, the installation of mechanical and electrical services might require:
- Cutting, forming or drilling through walls, floors or ceilings to allow services to pass.
- Ensuring structural integrity is not compromised.
- Chasing block and brickwork for conduits or pipes.
- Lifting and replacing floors.
- Asbestos removal.
- Plant moving services.
- Sealing holes.
- Reinstating fire, thermal or acoustic separation.
- Constructing plinths.
- Making good plaster and other finishes.
- Maintenance access requirements such as access panels, decking, platforms, cat ladders and handrails.
This may involve works that require building regulations approvals and possibly testing certificates (for example, cleaning cradle restraining bolts).
Builder's work in connection is generally carried out by the main contractor for a mechanical and electrical sub-contractor and other such specialist trades. However, sometimes, the mechanical and electrical works might be part of the main contract and the builders work in connection sub-contracted.
Builder’s work in connection should not be confused general site preliminaries such as; welfare provisions, site offices, plant, site waste clearance, and so on, which are priced separately.
Estimators typically price builder's work in connection as 7% of the specialist work value.
[edit] Related articles on Designing Buildings
Featured articles and news
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.