Arbitration v Adjudication
Construction contracts usually provide for disputes to be dealt with by agreed dispute resolution procedures. Arbitration and adjudication are two commonly-adopted forms of alternative dispute resolution ( ADR - that is, they do not involve litigation). Although the procedures adopted are similar, they should not be confused.
Arbitration is a procedure in which both sides agree to let an impartial third party, the arbitrator, decide the case. The arbitrator may be a lawyer, or may be an expert in the field of the dispute, or in some cases, an arbitration panel. The arbitrator’s decision, known as an award, is legally binding and can be enforced through the courts. Normally, there is no appeal, however there are exceptions in which appeals may be accepted. Arbitrators have the power to ascertain facts rather than just listen to submissions, and to order costs.
For more information see: Arbitration.
The Housing Grants, Construction and Regeneration Act imposes a right to adjudication in construction contracts. If parties to a construction contract do not agree an adjudication procedure, then one is imposed by the Scheme for construction contracts. In adjudication, the decision is the responsibility of a third party adjudicator selected by the parties to the dispute. Adjudication decisions are binding unless and until they are revised by subsequent arbitration or litigation after practical completion, or by agreement between the parties (hence the term 'pay now argue later'). There is no right of appeal and limited right to resist enforcement. Generally, adjudicators do not have the power to award costs (other than their own fees and expenses). Adjudication must adhere to strict timescales and typically takes up to 28 days.
For more information see: Adjudication.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.