Site selection and acquisition for construction
Site selection and acquisition is crucial when the client does not own the site to be developed. It should be undertaken as early as possible, ideally, in parallel with feasibility studies. This work may be carried out by a specialist consultant.
Key to the process is ensuring that the requirements for the site are properly defined, that the selected site meets these requirements and that it is acquired within the constraints of the project programme and with minimal risk to the client.
To achieve these objectives the following tasks need to be carried out:
- Preparing a statement of objectives/requirements for the site and facility/buildings and agreeing this with the client.
- Preparing a specification for site selection, establishing the criteria for evaluating sites based on the objectives/requirements and agreeing weightings with the client.
- Establishing the outline funding arrangements.
- Determining responsibilities within the project team (client/project manager/commercial property agent).
- Appointing/briefing members of the team and developing a schedule for site selection and acquisition; monitoring and controlling progress against the schedule.
- Actioning site searches and collecting data on sites, including local planning requirements, for evaluation against the criteria. See technical due diligence and site appraisals for more information.
- Evaluating sites against the criteria and producing a short list of three or four.
- Establishing initial options and developing costs.
- Discussing short-listed sites with relevant planning authorities.
- Obtaining advice on the approximate open-market value of short-listed sites.
- Selecting the preferred site from the short list.
- Appointing agents for price negotiation and separate agents for independent valuation.
- Appointing lawyers as appropriate.
- Determining specific financial arrangements.
- Exchanging contracts for site acquisition once terms are agreed, conditional upon relevant matters, such as ground investigation, planning consent and so on.
The text in this article is based on an extract from PROJECT MANAGEMENT, by Eric Stokes and Saleem Akram. The original manual was published in 2008. It was developed within the scope of the LdV program, project number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for European Managers in Construction”. It is reproduced here in a slightly modified form with the kind permission of the Chartered Institute of Building.
--CIOB
[edit] Related articles on Designing Buildings Wiki
- Applying for new postal addresses.
- Building People.
- Condition survey.
- Contaminated land.
- Developer.
- Gross development value.
- Ground conditions.
- Land acquisition.
- Overage.
- Overbuild.
- Restrictive covenants.
- Right of way.
- Site appraisal.
- Site information.
- Site surveys.
- Soil survey.
- Technical due diligence.
- Vacant possession.
- What is a housing start?
Featured articles and news
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.