Pre-contract meeting for construction contracts
The pre-contract meeting is an important meeting that takes place after the contractor has been appointed but before work commences on site. It is an opportunity for the project team to meet (perhaps for the first time) and to plan the construction stage.
The pre-contract meeting is chaired by the contract administrator and is an opportunity to:
- Make introductions and issue contact details (perhaps a project directory).
- Clarify roles, responsibilities and lines of communication.
- Agree meeting schedules, meeting structures and attendees.
- Hand over outstanding documents (such as insurance certificates and bonds) and issue outstanding information (which may including any variations made since the contract was awarded).
- Issue nomination instructions.
- Discuss the contractor's master programme, including incorporation of works outside of the main contract, inspections, commissioning and testing.
- Discuss the role of the project team members (including site inspectors).
- Agree procedures for monitoring, issuing, receiving and reviewing information (including the information release schedule if there is one, and its relationship with the contractor's master programme). This may include a distribution matrix.
- Agree site access procedures and issues.
- Agree site induction procedures and other health and safety issues.
- Agree procedures for dealing with queries.
- Agree procedures for issuing instructions.
- Hand over contractor's procurement schedule.
- Mobilisation schedule and status.
The meeting should be minuted so that there is a clear record of the procedures agreed and decisions made. These minutes may form part of the contract documents, subject to agreement by both parties.
See also: Consultant team start-up meeting and Specialist contractors start-up meeting.
[edit] Related articles on Designing Buildings Wiki
- Construction phase plan.
- Contract administrator.
- Contract documents.
- Contract negotiations.
- Contract strategy.
- Contractor's master programme.
- Handover to contractor.
- Health and safety.
- Information release schedule.
- Possession.
- Pre-contract management.
- Site inspectors.
- Site layout plan.
- Site waste management plan.
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.