Post project review of construction projects
A post project review may begin during the defects liability period, when the client first occupies the development (now called the 'rectification period' in Joint Contracts Tribunal (JCT) contracts).
A post project review is undertaken to evaluate the effectiveness and efficiency of the project delivery process. To undertake a post project review, it is important to seek the views of contractors, designers, suppliers and the client about how well the project was managed.
This may include assessments of how well the delivery of the project performed against key performance indicators such as:
- The quality of briefing documents.
- The effectiveness of communications.
- The performance of the entire project team.
- Quality issues.
- Health and safety issues.
- Certification.
- Variations.
- Claims and disputes.
- Collaborative practices.
An evaluation can then be made of what lessons can be learned from the approach taken and a lessons learned report prepared.
A wider 'post occupancy evaluation' may comprise two studies:
- A post project review to evaluate the project delivery process.
- An assessment of performance in use, to assess the extent to which business and design objectives have been satisfied, which may not begin until 6 to 12 months after occupation, as operations may not be properly established before then.
See Post occupancy evaluation and Performance in use for more information.
NB When the development is first occupied by the client, it is important to visit the site immediately to identify any issues that need to be addressed quickly. It can be beneficial to establish a help-desk and rapid response team to resolve issues as they arise (See articles on occupation and migration strategy).
[edit] Related articles on Designing Buildings Wiki
- BREEAM.
- Building performance metrics.
- Defects liability period.
- End of contract report.
- Energy performance certificates.
- Extended aftercare.
- Initial aftercare.
- OGC Gateway Review 5: Operations review & benefits realisation (or benefits evaluation)
- Migration strategy.
- Performance in use.
- Performance of exemplar buildings in use: Bridging the performance gap FB 78.
- Post occupancy evaluation (repeats some of the text in this article).
- Post opening project evaluation.
- Soft landings.
- Value added.
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.