Northern Ireland’s Central Procurement Directorate issues standard Z clauses for the NEC3
The Central Procurement Directive (CPD) in Northern Ireland has standardised the use of NEC Z clauses for central government construction work in Northern Ireland. The Guidance Note is an extremely valuable resource and is a model of how Z clauses should be incorporated.
Procurement Guidance Note 01/15 dated 8 May 2015 is an excellent example of how Z clauses for the NEC should be incorporated. Z clauses are frequently used to improperly transfer risk or to totally (if unintentionally) confuse the use of the NEC form of contract. However, they are not without merit. With the support of the NEC Users Group and the construction industry parties that engage with them in Northern Ireland, CPD has done a remarkable job of making the process of drafting Z clauses easier.
The Guidance Note is not copyrighted and offers a model for how others can and should adopt Z clauses. It includes a section for 28 typical Z clauses. The Note describes the “purpose” of each clause and gives some guidance as to how it is to be adopted. Some of the clauses are compulsory (for those subject to the Northern Ireland Procurement Policy) and others discretionary.
The Z clauses include many * that are relatively non-contentious and it goes some way to dealing with tricky issues such as two stage contracting (where there is a design which must be accepted before build commences) and the incorporation of a contractor’s quality submissions into the contractual framework.
However, it is arguable that further clarity could have been provided. The document could have:
- Clarified Secondary Option W2 on dispute resolution to make sure that it aligns with the law on adjudication; and
- Removed any ambiguity around the definition of a defect when the problem is the contractors’ service and/or their failure to comply with constraints rather than the actual work done.
Discretionary amendments to the compensation clauses are extremely light touch. There is no standardised amendment to the often changed Clause 19 and the only substantive change to the compensation event system is to move the risk of unforeseen physical conditions in 60.1(12) to the contractor in certain, tightly-defined circumstances.
On the positive side, the control of subcontractors, particularly in relation to those nominated by a contractor in a tendering process, is tightened up and the employer is given an express right to terminate for contraventions of bribery, fraud and the like – although this last point is prefaced as being optional which may cause the employer some difficulties. The “purpose” element of each Z clause, with the corresponding descriptions of intention, could be tightened up to make it clearer when a public authority should use the clauses but there can be absolutely no doubt this is a massive step forward for all in the industry.
The guidance note is essential reading for all NEC3 practitioners and procurers alike.
--Quigg Golden 09:37, 6 July 2015 (BST)
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.