Negotiated contract
In order to procure a building, a client will normally have to appoint a number of suppliers. There are a number of procedures that can be adopted to select and appoint suppliers.
- Open procedures.
- Selective procedures.
- Negotiated procedures.
- Serial procedures.
- Framework procedures.
Each has its own advantages and disadvantages which must be considered in relation to the particular objectives and scope of the project.
Some of these procedures involve competitive bidding between multiple contractors, whereas the negotiated procedure involves negotiations with just one pre-selected contractor.
In competitive bidding, a contract is agreed following a tendering process where the award is often made to the cheapest (or best value) tender. The concept of negotiation generally allows more flexibility for the client to select a contractor on a basis other than the lowest bid. Negotiated contracts are generally agreed between a contractor and client that have experience of working together and have a relationship built on trust.
Negotiating with a single supplier may be particularly appropriate for highly-specialist works where there may only be a limited number of potential suppliers, or for extending the scope of an existing contract. It can give the client the confidence of working with a supplier they already know, can reduce the duration and costs of tendering and can allow early supplier involvement.
As the design documents very often have not been completed at the negotiation stage, a cost plus contract or cost reimbursable contract is commonly used for negotiated tenders. This allows for the reimbursement of the contractor for the costs incurred during construction, such as labour, equipment and materials, as well as profit and overhead charges for the management of the project.
However, despite having the advantage of being more flexible, negotiated contracts can also be less attractive for clients who may see the lack of competitive tendering as driving up costs; though it is often the case that a strong working relationship with a contractor whose practice is well-known may more than make up for this over the duration of the project.
Negotiated contracts may not be permitted by some organisations due to the perceived lack of accountability. On public projects, or projects that include a publicly-funded element it may be necessary to advertise contracts.
Advantages:
- Client has flexibility in terms of choosing their preferred contractor.
- Time and cost savings involved in removing the tendering process.
- It can allow early supplier involvement.
- Contractor’s costs and pricing are more transparent as they are not seeking to win the bid purely on the lowest tender.
Disadvantages:
- There are fewer options for the client to choose between and so there may be less innovation.
- The costs may be driven up by the lack of competitive bidding.
- There is a heavy reliance on trust between the parties.
- Unless it is carefully structured and controlled, the negotiation process can create an adversarial atmosphere, even before the contract has been awarded.
- It can be seen as anti-competitive and exclusive, with the potential for ‘cozy’ relationships to develop between the client and the supplier.
[edit] Related articles on Designing Buildings Wiki:
- Back to back provisions in construction contracts.
- Competitive procedure with negotiation.
- Construction contract.
- Contract award.
- Contract negotiation.
- Contract strategy.
- Contractual documents.
- Cost plans.
- Design and build procurement route.
- Essentials of a contract.
- Fixed price construction contract.
- Form of tender.
- Major project construction contract.
- Negotiated Procedure without Prior Publication NPwPP.
- Negotiation techniques.
- Performance specification.
- Tender evaluation.
- Sub-contract.
- Whole-life costs.
[edit] External references
- Construction Management (4th ed.), HALPIN, D.W., SENIOR, B.A., Wiley, (2011)
Featured articles and news
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.