Contractual documents
This article lists the documents that are commonly required by or referred to in a construction contract. See also Contract documents for a list of the documents setting out the obligations and responsibilities of the parties to the contract on a traditionally-procured, fully-designed construction project,
In some cases, different contracts may use different names for the same document. Where this is the case, alternative names are shown.
- Application for payment (see Fair payment practices)
- Architect's instruction / contract administrator's instruction
- Bill of quantities
- Building log book
- Building owner's manual / operation and maintenance manual (O&M manual)
- Building users guide
- Certificate of making good defects / certificate of making good
- Collateral warranty
- Construction phase plan
- Contract sum analysis
- Contractors master programme
- Contractors proposals
- Default payment notice (see Fair payment practices)
- Contract drawings
- Design documents
- Employers requirements
- Final account
- Final certificate
- Health and safety file
- Information release schedule
- Insurance
- Interim certificate
- Joint fire code
- Method statement
- Pay less notice (see Fair payment practices)
- Payment notice (see Fair payment practices)
- Practical completion certificate / substantial completion certificate
- Preliminaries
- Risk assessment
- Schedule of defects
- Schedule of work
- Site waste management plan
- Specification
NB: A pre-contract meeting is likely to take place after the contractor has been appointed but before work commences on site. This is an opportunity to for the project team to meet (perhaps for the first time) and to plan the construction stage. The minutes of the pre-contract meeting may form part of contract documents (for all procurement routes) subject to the agreement of both parties.
See Pre-contract meeting for more information.
[edit] Related articles on Designing Buildings Wiki
- Bills of quantities.
- Construction contract.
- Contract conditions.
- Contract documents.
- Contractors proposals.
- Contract sum analysis.
- Employers requirements.
- Form of tender.
- Information release schedule.
- Performance bond.
- Pre-contract meeting.
- Procurement route.
- Schedules of work.
- Specifications.
- Tender.
- Tender documents.
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.