Meaning of lag in the construction industry
In the construction industry, the term ‘lag’ can mean:
- ‘…the minimum necessary lapse of time between the finish of one activity and the finish of another overlapping activity.' Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
- ‘…the amount of time required between the start or finish of a predecessor task and the start or finish of a successor task.’ Ref The Society of Construction Law Delay and Disruption Protocol.
- The delay in the transmission of thermal conditions between one side of the fabric of a building and the other.
- The process of installing insulation, in particular around water pipes to prevent freezing, or to prevent heat loss from hot water pipes. This is sometimes referred to as ‘lagging’.
- A type of screw or bolt: A heavy-duty fastener that creates its own mating thread in timber and other soft materials when tightened.
- A time delay between the action of a control system and its effect on the controlled parameter
[edit] Related articles on Designing Buildings
Featured articles and news
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.